Importing Cost Account

Sinan FahmiMember for 19 years 11 months
Created
6
41
0
Dear Planners,
is there any method to import cost account from excel to primavera p6, because my company has more than 2000 cost account and it will take a lot of time to type it one be one?

Regards,

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Sinan,
    Defining Account codes can be done by Excel SDK. If assigning account codes to activity you can use export/import excel spreadsheet functions in P6 using resource assignment.
  2. 0
    Sinan Fahmi ·
    Thanks my Friend,
    unfortunately I don’t know how to use Excel SDK, do you have any reference material that I can learn how to use this Kit.

    Thanks again for your reply
  3. 0
    Rodel Marasigan ·
    Sinan,

    There is a PP member offering Steps using SDK. Try to give him your email address and he might help.(link below)
    STEP-BY-STEP GUIDE USING SDK IN SCHEDULE PREPARATION
  4. 0
    John Reeves ·

    Can this be done now with

    Can this be done now with without an SDK.  It is crazy that you cannot import the cost accounts and costs.  I am simply importing the costs from an original file to a later file of the same name.  Costs import fine.  I will only import the cost accounts if you also import the WBS - and being that the WBS uses the project name, even though the same file that rev number is different and over-writes the WBS - how crazy is this.  Let me know if a way around this.  

  5. 0
    Zoltan Palffy ·

    you do nto need sdk all you

    you do nto need sdk all you need is the excel spreadsheet but p6 has to be on a 32 bit machine

Log in or join to reply