number of activities

M. Kamel BessekriMember for 17 years 4 months
Created
4
10
0

Hi all

are there  tips to get the number of the total activities and also per wbs level ?

thanks

4 replies

Oldest first
  1. 0
    Kumar S ·

    kamel you can find it in the

    kamel

    you can find it in the WBS layout .

    select total activities in the columns.

    cheers

  2. 0
    M. Kamel Bessekri ·

    Kumar thank you very much

    Kumar

    thank you very much

  3. 0
    Seyyit Eren Paydak ·

    Hi all,Or you can try

    Hi all,

    Or you can try "activity count" column..

    Regards..

    Eren Paydak

  4. 0
    Mathieu ALBOUY ·

    Activity Count in a column

    Activity Count in a column easy reachable (View Menu/Column/customize/ Available option).

    It works well and its availbale in Project, WBS, Activities view (the most usefull ones)