Total Float Bar on Completed Activities

Utku ÇilMember for 15 years 5 months
Created
2
23
0

Is there a way that I can remove the total float bar on completed activites?

I have an on-going schedule having completed, in progress & not started activities as can be predicted but I want to see the total float bar only for in progress & not started activities since, in my opinion, total float does not mean anything for completed activites.

Thanks in advance for who replies..

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    See extract from a Paul

    See extract from a Paul Harris presentation covering this:

     

  2. 0
    Utku Çil ·

    Thank you Gary,It seems to be

    Thank you Gary,

    It seems to be really simple as I guessed :)