Data that can not be modified by Excel?

Utku ÇilMember for 15 years 5 months
Created
2
23
0

Here comes another question Planners,

What specific data can not be modified by exporting to and importing back from Excel? For example, I could not change the Activity Type of a task using Excel. Is it because it can not be done or am I just doing sth wrong?

Thanks in advance.

2 replies

Oldest first
  1. 0
    David Kelly ·

    You cannot change activity

    You cannot change activity type.

     

    For a list of all the fields you can/cannot chnage - export all the fields.  Where there is a * in fron of the fields name

     

    e.g. (*)Activity Type

     

    The field cannot be imported and hence changed.

  2. 0
    Amit Parmar (PMP) ·

    Hi,You can use Primavera SDK

    Hi,

    You can use Primavera SDK "Activity sheet" to edit the Activity Type for your activities. If you need help using SDK then mssg me.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in