Need Help on Resource Usage Profile

Nik MuhammadMember for 15 years
Created
2
22
0

I need help...

Why my "Display Activities for selected..." function at bottom left pane in the Resource Usage Profile view is greyed out? I cant mark/click neither "Time Period" nor "Resource" options.

2 replies

Oldest first
  1. 0
    Mohammad Mojahid Akhtar ·

    dear nike go to right pan and

    dear nike

    go to right pan and click display and remove tick mark in "show all project".

    than yoy will find in left pan display activity for selected become on. ok

  2. 0
    Nik Muhammad ·

    It works! I have to uncheck

    It works! I have to uncheck "show all project" in the right bottom panel. Thanx a lot...

Log in or join to reply