P6 Calculation fixed unit/Time
In the Open Standard
walid LahianiMember for 16 years
- Created
- 5
- 18
0
GOood morning ,
This is the question
I changed the data date and pressed F9 =>the remaining duration didn't changed but at complete duration increased
I want that remaining duration change automatically so the remaining units in ressources increase and the formula
AT COMPLETE DURATION =Actual duration+Remaining duration still correct
thanks