Resource Usage Profile

Kannan CPMember for 18 years 4 months
Created
0
14
0

Hi,

I developed one programme with labour units input (resource). While preparing the resource distribution month wise, it was working smoothly from Toools- Report Wizard. But not working properly with Resource spread sheet.

Problem in detail:

1. From Tools- Report wizard, I ticked the box for average and put the value as 30(to divide) to get a monthwise average

2. When I tried the same using the Resource Using profile and put the value as 30 its still showing the cumulative only.

For eg: 30 man days in a month. as average 1 person (Tools-Report wizard calculation)

same showing as 30 with repource profile  (even with the average box ticked and value as 30)

Any ideas what may be wrong. I presume some tick box missing.

Regards

Kannan

 

 

Replies

Oldest first

No replies yet. Be the first to answer.