Is it possible to export a calendar from primavera 6? if yes. how i can do it?

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Streetboy, Here ist it.

    Streetboy,

    Here ist it.

  2. 0
    Alexandre Faulx-Briole ·

    Streetboy,if the calendar you

    Streetboy,

    if the calendar you want to export is used by a specific project, export this project will export the calendar too

    it would be safe to give the calendar a new name, it will be easier to find it when you import the project

    you will delete the project afterwards

    Alexandre

  3. 0
    Tim Readman ·

    You can export a calendar

    You can export a calendar from P6 into a PDF form which will show the working days from the day one of the project to take into account all non working days. In p3 you could see this but not in P6 even up to version 8.2

     

    try  this website

     

    http://comviz.com.au/ 

     

  4. 0
    Tim Readman ·

    You can export a calendar

    You can export a calendar from P6 into a PDF form which will show the working days from the day one of the project to take into account all non working days. In p3 you could see this but not in P6 even up to version 8.2

     

    try  this website

     

    http://comviz.com.au/ 

     