Resource assignment in P6 V7 is not as assigned calendar hours
- Created
- 1
- 24
Hi,
I am preparing a program for a small job. The effective work hours per day is 7.5 and 6.5days per week. I have set the calendar for that which I have assigned to all my resources and activities as well. I have ticked the tab to use assigned calendar to specify the number of work hours for each time period in Admin Prefrences. Now my issue is with the output in resource assignment. As my calendar says to work 7.5hrs/day to the resource but the resource assignmet window gives me budgeted hours for each resource based on 5.63hrs/day. So I am not getting 7.5hrs/day working for particular resource.
Can any one please help me why this is happening?
Thanks in advance.
Nilkamal