Skip to content

Question Regarding Cost Loading in Primavera P6 ?

Irfan KhanMember for 17 years 3 months
Created
4
26
0

hi to all experts,

 
I am working with a recovery schedule. Which has been progressed upto 23.50%.
 
Now scope of my contract has been changed.
before total project value was 50 millions.
now after lots of change order it is 70 millions.
& invoice already claimed upto 50% 
 
my question is should i load total revised cost i.e. 70 million on my schedule or should i load cost based on remaining work.
 
any promptly reply will be highly appreciated.
 
thanx in advance......

4 replies

Oldest first
  1. 0
    Shiguo Zhang ·

    hi Irfan I think you should

    hi Irfan

    I think you should load total revised cost .  I am new to P6, so it's just an advice.

  2. 0
    Raymund de Laza ·

    Irfan,Load the Actual in the

    Irfan,

    Load the Actual in the left side and remaining in the right side of the DD....

  3. 0
    Srichand Sobhani ·

    Hi Irfan,Agree with Raymund

    Hi Irfan,

    Agree with Raymund reply, total cost to be loaded and remaining shall show whatever balance per activity from data date.

    Regards,

    Sri

  4. 0
    Rowstone Fausto ·

    Load only whatever cost added

    Load only whatever cost added to remaining activities. Forget the cost for all completed activities, it is considered a sunk cost. Planning is iterative so while the project is progressing you need to replan, catchup the schedule and recompute the remaining level of efforts needed to complete your project. Make original durations intuitive equal to remaining.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?