Methods of Construction (C. INTERIORS)

Hussein ObeyMember for 21 years 3 months
Created
5
5
0
Dear All,

Reference to my previous posting for Methods of Construction and that no one has shared the issue except for "Sukumaran Subaramaniyan" who advised to breack down the subject and to focus on objectives.

Our objectives are to formulate the method statement for different construction project items as a step towards standardizing scheduling practice. Then to publish this manual among all planning planet members to be circulated as a property for planning planet community.

We here are talking about "C. INTERIORS" which as a start may be brokedown as follows:

C. INTERIORS
C10 Interior Construction
C1010 Partitions
C1020 Interior Doors
C1030 Specialties
C20 Staircases
C2010 Stair Construction
C2020 Stair Finishes
C30 Interior Finishes
C3010 Wall Finishes
C3020 Floor Finishes
C3030 Ceiling Finishes

This is our project and you all will be proud of it.

Thank you,

Your’s,
Hussein, M.Sc. in construction management.
hamaksoud@yahoo.com

5 replies

Oldest first
  1. 0
    Khaled Bashiti ·
    Hi Hussein,

    unfortunetly the way u r presenting the issue confuse the viewers, if u want to do a method statement for Interior works or for Furniture or MEP or Structure you can’t just come and list Codes.

    Simply say i need to get information concerning this subject whats the best way to deal with.

    Answers will fly over from all memebers.

    to push members to participate u should guide them with a startup

    Example:

    Method statement for Interiors u have to differntiate between Finishes, Fit-outs & Furnitures & Equipments.

    Usually what can we say is the best way to proceed with work in a Hotel(specify the project because u have a large scale of jobs)even which part of a Hotel Typical Floors

    how u will do the Works simply we will break Each Level of the Typical Floors into Zones(1- Main Corridor, Lift Looby, & Room Enterance all Togather. 2- Rooms. 3- Toilets. 4- Service Rooms) this break down it depends upon the included trades means: each zone have its own MEP works also Finishes, Fit-outs, & Furnitures automatically the crews can be divided into those zones.

    So We have to Specify the 1- Project Type 2- Trade 3- Zone
    4- Gangs Flow

    Depending at Project type each one can put his input, also according to Trade.

    hope that i have helped without any misunderstanding.
    regards,













  2. 0
    Hussein Obey ·
    Dear Mr. Khaled Bashiti, Dear All,

    Thank you very much on your response in our brainstorming.

    1. You are right, the subject needs to be more simplified and clear with definite form and deliverables and I am working on that.

    2. The WBS I suggested depended on the Idea of standardization not on specific type of structure, location,.... the output we hope to get out of this brainstorming is a categorized list of all workpackages that a planning engineer may face in any project with the method of construction of each. When the planner works on a real world project he will select only packages included in his project and put them in the appropriate location in his project WBS.

    If we considered your example:

    1. The realworld project will be an Hotel with the following potion of a WBS:

    + Hotel Project
    + Basement
    ....
    + Ground floor
    ....
    + Firtst floor
    + Main Corridor,Lift Looby,Room Enterance
    ....
    + Rooms
    ....
    + Toilets
    - MEP works
    - Finishes
    - Fit-outs
    - Furnitures
    + Service Rooms
    ....

    2. Deliverables in our project will be organized in a standardized fashion not in a projectized fashion to include all possible types of work under each category (Uniformat) as shown totally in my topic "Methods of Construction" on this forum.

    for example: the Planner in the realworld project (the above shown WBS) needs the MEP, Finishes, Fit-outs and Furnitures not only once but several times according to instances of occurance on the project but he will find each one in only one location in out "project for standardization" he will find:

    - MEP in Item D of the Uniformat (shown in my topic "Methods of Construction")

    - Equipment in Item E of the Uniformat (shown in my topic "Methods of Construction")

    - Finishes and fit-outs in Item C of the Uniformat (shown in my topic "Methods of Construction")

    and so on.

    3. The planner takes all his packages and palce them where ever needed in his realworld project.

    -----------------------------------------------------------

    The question now is "What do we mean exactly with Method of construction?"

    Well, The initial meaning I suggest to start with is (According to PMI-PMBOK 2000):
    - List of activities including prerequisits.
    - Activity Sequence (either mandatory or discretionary).
    - Resources required (including material, labor, equipment).
    - Factors to be considered for duration estimation.
    - Lags or leads that may be required.
    - Risk factors in metrics of cost and time impact.

    Mr. Khaled Thanks a lot and I hope to receive more of your responses and ideas to help in completing this project.

    Thank you All,

    Hussein Abdel Maksoud, MSc Construction Management.
    hamaksoud@yahoo.com
  3. 0
    Khaled Bashiti ·
    Hi Hussein,

    As a begining stop dividing the subject and copying it to another Posts. i understand that u want to differentiate between different trades but this will not help.

    What really help is that u atleast start with one trade then once its finished u can start the other ones, where u will find that 60% of information for the next trade was discussed, because trades sequence is like a net.

    So just start with one trade if i m not mistaken Start with Construction and leave the Pre-Construction(MasterPlan, Design & Engineering,Tendering)to a later stage.

    as u have categorized yr Method Statement lets start on:

    1- List of activities including prerequisits.

    Civil & Infrastructure Works for Terrestrial(Marine Works will Need another Category):

    - Mobilization
    - Enabling Works
    - Enviromental Remediation Works
    - Land Reclamination & Mass Grading
    - Infrastructure Works
    - Building Structure
    (Lets Start listing activities for the above ones, as u know they can be built from a huge number of activities, this was a start-up)

    as for the hereunder catergories lets add ther comments also.

    2- Activity Sequence (either mandatory or discretionary).
    3- Resources required (including material, labor, equipment).
    4- Factors to be considered for duration estimation.
    5- Lags or leads that may be required.
    6- Risk factors in metrics of cost and time impact.


    Its a huge job it need patient and time, but its a startup.

    regards,

  4. 0
    Hussein Obey ·
    Hi all,
    Hi Mr Khaled
    Hi Mr Sukumaran Subaramaniyan

    I intend to set some kind of rewarding system as a motivation for our selves to work on this project.
    So, I need to formulate an evaluation committee to evaluate posts then based on the committee evaluation the Planner will win the reward for each approved post.

    -----------
    The Reward:
    -----------
    All participants that their posts are approved by the committee will win a valuable Project Management Book and have the right to select one of the following books:
    - McGraw Hill - Project Management
    - Mcgraw-Hill The Six Sigma Project Planner Ebook
    - AMACON - Modern Project Management
    - Project Management - New Six Sigma - A Leader Guide To Achieving Rapid Business (Prentice Hall)
    - Project Management - The Evolutionary Project Manager’s Handbook
    - Project Management - The Project Manager’s MBA
    - Project Management Manual
    - Project Management Skills
    - Project Manager Manual
    - Wiley - Practical Project Management
    - Wiley - Project Management Methodologies

    So, Mr Khaled,Mr Sukumaran Subaramaniyan I invite you to be the first two members of the A/M committee so, please if you agree let me know.

    All members can begin posts submition and receiving rewards from now. temporarily I will evaluate the posts till the committee is founded and any one of the members is encouraged to sent his evaluation to any post.

    Thank You all,

    Hussein Abdel Maksoud, M.Sc. construction Management
    hamaksoud@yahoo.com
  5. 0
    Milind Pandhare ·
    Activity ID Activity description
    MOBI-01 Site Mobilisation
    MOBI-03 Fencing work
    MOBI-02 Establish Temporary Servicies
    EARTH-03 Shoring ( I- Section Concrete pannel )
    EARTH-02 Priliminary Earth Work
    EARTH-04 1st Phase Excavation
    EARTH-05 2nd stage Excavation & concrete panel instlation
    EARTH-07 Carting Excess Excavated material
    EARTH-06 Dewaterring
    EARTH-08 Formation of Deep Area
    EARTH-09 Compaction & Formation for Raft bed
    FOUND-02 Guniting
    FOUND-01 PCC Deep Area
    FOUND-03 PCC below RAFT
    FOUND-05 Rubberised Bitumen Coating
    FOUND-06 Waterproofing & Screed Protection
    FOUND-04 Vertical area water proffing
    FOUND-07 Steel work for RAFT
    MEP-01 Drainage pipe laying and testing (UG Drainage)
    FOUND-08 Raft Slab Casting (Part A&B)
    SUB-01 Retaining Wall
    SUB-06 Ramp Work
    SUB-02 Shear Wall & Lift Core Wall
    SUB-03 steel work for column
    SUB-04 Form work for column
    SUB-05 Column casting For GF Slab
    SUB-07 Decking Work for G.F Slab
    SUB-08 Steel Work for G.F Slab
    SUB-09 MEP sleves & conduits for G.F Slab
    SUB-10 Ground Floor Slab Casting
    SUB-11 Deshuttering
    SUB-12 Ramp Side RCC wall
    SUB-13 Rcc planters & side wall / upstaand
    SUCO-GF-02 steel work for column/A
    SUCO-GF-03 Form work for column/A
    SUCO-GF-01 Shear Wall /A
    SUCO-GF-04 Column casting For 1F/A Slab
    SUCO-GF-05 Decking work for 1F/ASlab
    SUCO-GF-07 Steel Work for 1F/A Slab
    SUCO-GF-08 MEP sleves & conduits for 1.F/A Slab
    SUCO-GF-09 First Floor Slab Casting[Part-A ]
    SUCO-GF-10 Deshuttring PART- A
    SUCO-GF-12 steel work for column
    SUCO-GF-11 Shear Wall & Lift Core Wall
    SUCO-GF-13 Form work for column
    SUCO-GF-14 Column casting For 1F Slab
    SUCO-GF-15 Decking work for 1F Slab
    SUCO-GF-17 Steel Work for 1F Slab
    SUCO-GF-18 MEP sleves & conduits for 1.F Slab
    SUCO-GF-19 First Floor Slab Casting[Part-B ]
    SUCO-GF-20 Deshuttering PART- B
    SUCO-GF-16 Ramp Side RCC wall
    SUCO-1F-01 steel work for column/A
    SUCO-1F-02 Form work for column/A
    SUCO-1F-03 Shear Wall /A
    SUCO-1F-04 Column casting For 2F/A Slab
    SUCO-1F-05 Decking work for 2F/ASlab
    SUCO-1F-06 Steel Work for 2F/A Slab
    SUCO-1F-07 MEP sleves & conduits for 2.F/A Slab
    SUCO-1F-08 Second Floor Slab Casting[Part-A ]
    SUCO-1F-09 Deshuttering PART- A
    SUCO-1F-11 Steel work for column
    SUCO-1F-12 Form work for column
    SUCO-1F-10 Shear Wall & Lift Core Wall
    SUCO-1F-13 Column casting For 2F Slab
    SUCO-1F-14 Decking Work for 2F Slab
    SUCO-1F-15 Steel Work for 2F Slab
    SUCO-1F-16 MEP sleves & conduits for 2 F Slab
    SUCO-1F-17 Second Floor Slab Casting [Part-B ]
    SUCO-1F-18 Deshuttering PART- B
    SUCO-2F-01 steel work for column/A
    SUCO-2F-02 Form work for column/A
    SUCO-2F-03 Shear Wall /A
    SUCO-2F-04 Column casting For 3F/A Slab
    SUCO-2F-05 Decking work for3F/ASlab
    SUCO-2F-06 Steel Work for3F/A Slab
    SUCO-2F-07 MEP sleves & conduits for 3 F/A Slab
    SUCO-2F-08 ThirdFloor Slab Casting[Part-A ]
    SUCO-2F-09 Third floor slab Deshuttering PART- A
    SUCO-2F-11 steel work for column
    SUCO-2F-10 Shear Wall
    SUCO-2F-12 Form work for column
    SUCO-2F-13 Column casting For 3F Slab
    SUCO-2F-14 Decking Work for 3F Slab
    SUCO-2F-15 Steel Work for 3F Slab
    SUCO-2F-16 MEP sleves & conduits for 3F Slab
    SUCO-2F-17 Third Floor Slab Casting [Part-B]
    SUCO-2F-18 Deshuttering PART- B
    SUCO-3F-01 steel work for column/A
    SUCO-3F-02 Form work for column/A
    SUCO-3F-03 Shear Wall /A
    SUCO-3F-04 Column casting For 4F/A Slab
    SUCO-3F-05 Decking work for 4F/ASlab
    SUCO-3F-06 Steel Work for4F/A Slab
    SUCO-3F-07 MEP sleves & conduits for4.F/A Slab
    SUCO-3F-08 Fourth Floor Slab Casting[Part-A ]
    SUCO-3F-09 Deshuttering PART- A
    SUCO-3F-11 steel work for column
    SUCO-3F-10 Shear Wall & Lift Core Wall
    SUCO-3F-12 Form work for column
    SUCO-3F-13 Column casting For 4F Slab
    SUCO-3F-14 Decking Work for 4F Slab
    SUCO-3F-15 Steel Work for 4F Slab
    SUCO-3F-16 MEP sleves & conduits for 4F Slab
    SUCO-3F-17 Fourth Floor Slab Casting [Part-B
    SUCO-3F-18 Deshuttering 4 F slab PART- B
    SUCO-4F-01 steel work for column/A
    SUCO-4F-02 Form work for column/A
    SUCO-4F-03 Shear Wall /A
    SUCO-4F-04 Column casting For5F/A Slab
    SUCO-4F-05 Decking work for 5F/ASlab
    SUCO-4F-06 Steel Work for 5F/A Slab
    SUCO-4F-07 MEP sleves & conduits for 5F/A Slab
    SUCO-4F-08 Fifth Floor Slab Casting[Part-A ]
    SUCO-4F-09 Deshuttering PART- A
    SUCO-4F-11 steel work for column
    SUCO-4F-10 Shear Wall & Lift Core Wall
    SUCO-4F-12 Form work for column
    SUCO-4F-13 Column casting For 5F Slab
    SUCO-4F-14 Decking Work for 5.F Slab
    SUCO-4F-15 Steel Work for 5.F Slab
    SUCO-4F-16 MEP sleves & conduits for 5.F Slab
    SUCO-4F-17 Fifth Floor Slab [Part-B]
    SUCO-4F-18 Deshuttering 5F Slab PART- B
    SUCO-5F-01 steel work for column/A
    SUCO-5F-02 Form work for column/A
    SUCO-5F-03 Shear Wall /A
    SUCO-5F-04 Column casting For 6F/A Slab
    SUCO-5F-05 Decking work for 6F/ASlab
    SUCO-5F-06 Steel Work for 6F/A Slab
    SUCO-5F-07 MEP sleves & conduits for 6 F/A Slab
    SUCO-5F-08 Sixth Floor Slab Casting[Part-A ]
    SUCO-5F-09 Deshuttering PART- A
    SUCO-5F-11 steel work for column
    SUCO-5F-10 Shear Wall & Lift Core Wall
    SUCO-5F-12 Form work for column
    SUCO-5F-13 Column casting For 6 F Slab
    SUCO-5F-14 Decking Work for 6.F Slab
    SUCO-5F-15 Steel Work for 6.F Slab
    SUCO-5F-16 MEP sleves & conduits for 6.F Slab
    SUCO-5F-17 Sixth Floor Slab Casting PART-B
    SUCO-5F-18 Deshuttering PART- B
    SUCO-6F-01 steel work for column/A
    SUCO-6F-02 Form work for column/A
    SUCO-6F-03 Shear Wall /A
    SUCO-6F-04 Column casting For 7F/A Slab
    SUCO-6F-05 Decking work for 7F/ASlab
    SUCO-6F-06 Steel Work for 7F/A Slab
    SUCO-6F-07 MEP sleves & conduits for 7F/A Slab
    SUCO-6F-08 Seventh Floor Slab Casting[Part-A ]
    SUCO-6F-09 Deshuttering PART- A
    SUCO-6F-11 steel work for column
    SUCO-6F-10 Shear Wall & Lift Core Wall
    SUCO-6F-12 Form work for column
    SUCO-6F-13 Column casting For 7F Slab
    SUCO-6F-14 Decking Work for 7.F Slab
    SUCO-6F-15 Steel Work for 7.F Slab
    SUCO-6F-16 MEP sleves & conduits for 7.F Slab
    SUCO-6F-17 Seventh Floor Slab Casting (PART-B)
    SUCO-6F-18 Deshuttering PART- B
    SUCO-7F-01 steel work for column/A
    SUCO-7F-02 Form work for column/A
    SUCO-7F-03 Shear Wall /A
    SUCO-7F-04 Column casting For RF /A Slab
    SUCO-7F-05 Decking work for RF/A Slab
    SUCO-7F-06 Steel Work for RF/A Slab
    SUCO-7F-07 MEP sleves & conduits for RF/A Slab
    SUCO-7F-08 Roof Floor Slab Casting[Part-A ]
    SUCO-7F-09 Deshuttering PART- A
    SUCO-7F-11 steel work for column
    SUCO-7F-10 Shear Wall & Lift Core Wall
    SUCO-7F-12 Form work for column
    SUCO-7F-13 Column casting For RF Slab
    SUCO-7F-14 Decking Work for R.F Slab
    SUCO-7F-15 Steel Work for R.F Slab
    SUCO-7F-16 MEP sleves & conduits for R.F Slab
    SUCO-7F-17 Roof Slab Casting (PART-B)
    SUCO-7F-18 Deshuttering PART- B
    SUCO-HC-01 steel work for column
    SUCO-HC-02 Shear Wall & Lift Core Wall
    SUCO-HC-03 Form work for column
    SUCO-HC-05 Parapet Wall
    SUCO-HC-04 Column casting
    SUCO-HC-07 Swimming pool Shell
    SUCO-HC-10 Pool Deck
    SUCO-HC-06 Decking Work for HC Slab
    SUCO-HC-09 MEP sleves & conduits for HC Slab
    SUCO-HC-08 Steel Work for HC Slab
    SUCO-HC-11 Helth Club Slab Casting
    SUCO-HC-12 Deshuttering
    SUCO-UR-03 steel work for column
    SUCO-UR-02 Shear Wall & Lift Core Wall
    SUCO-UR-04 Form work for column
    SUCO-UR-05 Parapet Wall above HC
    SUCO-UR-01 Column casting For lift m/c room
    SUCO-UR-06 Decking Work for lift m/c room
    SUCO-UR-08 MEP sleves & conduits for lift m/c room
    SUCO-UR-07 Steel Work for lift m/c room
    SUCO-UR-09 Lift m/c room Slab
    BLO-B-01 cleaning
    BLO-B-02 Block layout and checking
    BLO-B-03 Block work in Basement
    BLO-B-04 R.C.C Lintel
    PLAS-B-01 Wall Plaster - Basement
    PLAS-B-02 Celing Plaster-Basement
    FLO-B-02 marble flooring to lift loby
    A0EXAV-09 Earth filling above raft 8’’tk
    FLO-B-04 Marble Wall Clading to Lift Loby
    FLO-B-05 4’’ PCC with mesh
    FLO-B-07 Pump/ Store room flooring
    FLO-B-01 Car parking /Driveway Floor Finishing
    FLO-B-03 floor finish to water tank area
    FLO-B-06 Wall clading to Pump room
    FLO-B-08 Thrishold
    FAL-B-01 False Ceiling
    PANT-B-01 Internal wall & ceiling painting
    PANT-B-02 Anticarbonation painting in wall
    PANT-B-03 Final internal painting
    CARP-B-01 Fixing of Door Frame
    CARP-B-02 Fixing of Door Shutter
    A0MIS-01 Substation Trenching Work
    MET-01 Aluminium (LOUVER WORK) Substation
    PANT-GF-01 Transformer room painting
    A0PRO-17 Dewa Inspection Substation
    A0PRO-18 Sub station hand over to DEWA
    BLO-GF-01 cleaning
    BLO-GF-02 Block layout and checking
    BLO-GF-03 Internal Block Work
    BLO-GF-04 Block work- GF
    A0ON-GF-08 R.C.C Lintel
    PLAS-GF-02 Celing Plaster- GF
    PLAS-GF-01 Wall Plaster GF
    WPR-GF-02 GF- Parking W/P
    WPR-GF-01 Water proof coating to Wet areas
    WPR-GF-03 Vertical side w/p of wet area
    FLO-GF-08 Wet area wall clading ( garbage room)
    FLO-GF-06 Wet area flooring (ceramic tiles)
    WPR-GF-04 Water proofing to substation slab roof
    FLO-GF-02 Floor Screed for Electrical Room/gym/
    FLO-GF-01 4’’ PCC with mesh
    FLO-GF-03 Floor Screed for M.hall
    FLO-GF-05 Floor Screed for Electricaal Sub-station
    FLO-GF-04 Car parking /Driveway Floor Finishing
    FLO-GF-07 Floor Screed for Gym / Shop
    FLO-GF-09 Mosaic flooring to stair floor & landing area
    FLO-GF-10 Floor Screed for Gen. Room
    FLO-GF-11 Store and other room flooring
    FLO-GF-12 mosaic step
    FLO-GF-14 Marble flooring to Entrance passage
    FLO-GF-15 mosaic skirting for steps
    FLO-GF-13 Threshold
    FLO-GF-17 Fixing Marble Steps
    FLO-GF-16 Marble Wall Clading to Lift Loby
    FAL-GF-01 False Ceiling
    PANT-GF-02 Internal wall & ceiling painting
    PANT-GF-03 Final internal painting
    PANT-GF-04 Anticarbonation painting in wall
    CARP-GF-01 Fixing of Door Frame
    CARP-GF-02 Fixing of Door Shutter
    CARP-GF-03 Fixing of Kitchen Cabinet
    CARP-GF-04 Fixing of Wardrobes
    MEP-GF-07 Sanitary fixing & Mixer
    BLO-1F-01 Cleaning
    BLO-1F-02 Block layout and checking
    BLO-1F-04 Block work- 1F
    BLO-1F-03 Internal Block Work
    A0ON-1F-07 R.C.C Lintel
    PLAS-1F-02 Celing Plaster- 1F
    PLAS-1F-01 Wall Plaster - 1F
    WPR-1F-02 Water proof coating to Wet areas
    WPR-1F-03 Vertical side w/p of wet area
    FL0-1F-10 Wet area -Ceramic Wall Clading
    FL0-1F-04 Wet area- Ceramic flooring
    FL0-1F-02 Floor Screed for Electrical Room
    FL0-1F-01 Ceramic flooring inside room
    FL0-1F-03 Ceramic tiling to balconey and terrase
    FL0-1F-05 Ceramic tile to entrance loby
    FL0-1F-06 Marble flooring to Corridor
    FL0-1F-07 Skirting
    FL0-1F-09 Corridor Wall Clading-Ceramic
    FL0-1F-08 Telephone room & other room flooring
    FL0-1F-11 Threshold
    FAL-1F-01 1F-Baalcony False Ceiling
    FAL-1F-02 False Ceiling
    PANT-1F-01 Internal wall & ceiling painting
    PANT-1F-02 Final internal painting
    CARP-1F-01 Fixing of Door Frame
    CARP-1F-02 Fixing of Door Shutter
    CARP-1F-03 Fixing of Kitchen Cabinet
    CARP-1F-04 Fixing of Wardrobes
    MEP-1F-08 Bath Tub Fixing
    MEP-1F-09 Sanitary fixing & Mixer
    BLO-2F-01 clening
    BLO-2F-02 Block layout and checking
    BLO-2F-04 Block work- 2F
    BLO-2F-03 Internal Block Work
    A0ON-2F-07 R.C.C Lintel
    PLAS-2F-01 Wall Plaster - 2F
    PLAS-2F-02 Celing Plaster- 2F
    WPR-2F-02 Water proof coating to Wet areas
    WPR-2F-03 Vertical side w/p of wet area
    FLO-2F-10 Wet area -Ceramic Wall Clading
    FLO-2F-05 Wet area- Ceramic flooring
    FLO-2F-01 Ceramic tile to entrance loby
    FLO-2F-02 Floor Screed for Electrical Room
    FLO-2F-03 Ceramic tile iside the room
    FLO-2F-04 Ceramic tiling to balconey and terrase
    FLO-2F-06 Marble flooring to Corridor
    FLO-2F-07 Skirting
    FLO-2F-09 Corridor Wall Clading-Ceramic
    FLO-2F-08 Telephone room & other room flooring
    FLO-2F-11 Threshold
    FAL-2F-01 2F-Baalcony False Ceiling
    FAL-2F-02 False Ceiling
    PANT-2F-01 Internal wall & ceiling painting
    PANT-2F-02 Final internal painting
    CARP-2F-01 Fixing of Door Frame
    CARP-2F-02 Fixing of Door Shutter
    CARP-2F-03 Fixing of Kitchen Cabinet
    CARP-2F-04 Fixing of Wardrobes
    MEP-2F-08 Bath Tub Fixing
    MEP-2F-09 Sanitary fixing & Mixer
    BLO-3F-01 cleaning
    BLO-3F-02 Block layout and checking
    BLO-3F-03 Block work -3F
    BLO-3F-04 Internal Block Work
    A0ON-3F-07 R.C.C Lintel
    PLAS-3F-01 Wall Plaster - 3F
    PLAS-3F-02 Celing Plaster- 3F
    WPR-3F-02 Water proof coating to Wet areas
    WPR-3F-03 Vertical side w/p of wet area
    FLO-3F-08 Wet area -Ceramic Wall Clading
    FLO-3F-03 Wet area- Ceramic flooring
    FLO-3F-01 Ceramic tiling to balconey and terrase
    FLO-3F-02 Ceramic tile iside the room
    FLO-3F-06 Floor Screed for Electrical Room
    FLO-3F-04 Ceramic tile to entrance loby
    FLO-3F-05 Skirting
    FLO-3F-07 Telephone room & other room flooring
    FLO-3F-09 Marble flooring to Corridor
    FLO-3F-10 Threshold
    FLO-3F-11 Corridor Wall Clading-Ceramic
    FAL-3F-01 3F-Baalcony False Ceiling
    FAL-3F-02 False Ceiling
    PANT-3F-01 Internal wall & ceiling painting
    PANT-3F-02 Final internal painting
    CARP-3F-01 Fixing of Door Frame
    CARP-3F-02 Fixing of Door Shutter
    CARP-3F-03 Fixing of Kitchen Cabinet
    CARP-3F-04 Fixing of Wardrobes
    MEP-3F-08 Bath Tub Fixing
    MEP-3F-09 Sanitary fixing & Mixer
    BLO-4F-01 cleaning
    BLO-4F-02 Block layout and checking
    BLO-4F-04 Block work -4F
    BLO-4F-03 Internal Block Work
    A0ON-4F-07 R.C.C Lintel
    PLAS-4F-01 Wall Plaster - 4F
    PLAS-4F-02 Celing Plaster- 4F
    WPR-4F-02 Water proof coating to Wet areas
    WPR-4F-03 Vertical side w/p of wet area
    FLO-4F-09 Wet area -Ceramic Wall Clading
    FLO-4F-08 Wet area- Ceramic flooring
    FLO-4F-02 Floor Screed for Electrical Room
    FLO-4F-01 Ceramic tile to entrance loby
    FLO-4F-03 Ceramic tiling to balconey and terrase
    FLO-4F-05 Marble flooring to Corridor
    FLO-4F-04 Ceramic tile iside the room
    FLO-4F-10 Telephone room & other room flooring
    FLO-4F-06 Corridor Wall Clading-Ceramic
    FLO-4F-07 Skirting
    FLO-4F-11 Threshold
    FAL-4F-01 4F-Balcony False Ceiling
    FAL-4F-02 False Ceiling
    PANT-4F-01 Internal wall & ceiling painting
    PANT-4F-02 Final internal painting
    CARP-4F-02 Fixing of Door Frame
    CARP-4F-03 Fixing of Door Shutter
    CARP-4F-01 Fixing of Kitchen Cabinet
    CARP-4F-04 Fixing of Wardrobes
    MEP-4F-08 Bath Tub Fixing
    MEP-4F-09 Sanitary fixing & Mixer
    BLO-5F-01 cleaning
    BLO-5F-02 Block layout and checking
    BLO-5F-04 Block work -5F
    BLO-5F-03 Internal Block Work
    A0ON-5F-07 R.C.C Lintel
    PLAS-5F-01 Wall Plaster - 5F
    PLAS-5F-02 Celing Plaster- 5F
    WRP-5F-02 Water proof coating to Wet areas
    WRP-5F-03 Vertical side w/p of wet area
    FLO-5F-10 Wet area -Ceramic Wall Clading
    FLO-5F-04 Wet area- Ceramic flooring
    FLO-5F-01 Floor Screed for Electrical Room
    FLO-5F-03 Ceramic tile to entrance loby
    FLO-5F-06 Marble flooring to Corridor
    FLO-5F-05 Ceramic tile iside the room
    FLO-5F-02 Ceramic tiling to balconey and terrase
    FLO-5F-08 Telephone room & other room flooring
    FLO-5F-07 Corridor Wall Clading-Ceramic
    FLO-5F-09 Skirting
    FLO-5F-11 Threshold
    FAL-5F-01 5F-Balcony False Ceiling
    FAL-5F-02 False Ceiling
    PANT-5F-01 Internal wall & ceiling painting
    PANT-5F-02 Final internal painting
    CARP-5F-02 Fixing of Door Frame
    CARP-5F-03 Fixing of Door Shutter
    CARP-5F-01 Fixing of Kitchen Cabinet
    CARP-5F-04 Fixing of Wardrobes
    MEP-5F-08 Bath Tub Fixing
    MEP-5F-09 Sanitary fixing & Mixer
    BLO-6F-01 cleaning
    BLO-6F-02 Block layout and checking
    BLO-6F-03 Block work -6F
    BLO-6F-04 Internal Block Work
    A0ON-6F-07 R.C.C Lintel
    PLAS-6F-01 Wall Plaster - 6F
    PLAS-6F-02 Celing Plaster- 6F
    WRP-6F-02 Water proof coating to Wet areas
    WRP-6F-03 Vertical side w/p of wet area
    FLO-6F-11 Wet area -Ceramic Wall Clading
    FLO-6F-05 Wet area- Ceramic flooring
    FLO-6F-01 Floor Screed for Electrical Room
    FLO-6F-03 Ceramic tile to entrance loby
    FLO-6F-04 Ceramic tile iside the room
    FLO-6F-02 Ceramic tiling to balconey and terrase
    FLO-6F-06 Skirting
    FLO-6F-09 Marble flooring to Corridor
    FLO-6F-10 Corridor Wall Clading-Ceramic
    FLO-6F-07 Telephone room & other room flooring
    FLO-6F-08 Threshold
    FAL-6F-01 6F-Balcony False Ceiling
    FAL-6F-02 False Ceiling
    PANT-6F-01 Internal wall & ceiling painting
    PANT-6F-02 Final internal painting
    CARP-6F-01 Fixing of Door Frame
    CARP-6F-02 Fixing of Door Shutter
    CARP-6F-03 Fixing of Kitchen Cabinet
    CARP-6F-04 Fixing of Wardrobes
    MEP-6F-08 Bath Tub Fixing
    MEP-6F-11 Sanitary fixing & Mixer
    BLO-7F-01 cleaning
    BLO-7F-02 Block layout and checking
    BLO-7F-03 Block work -7F
    BLO-7F-04 Internal Block Work
    A0ON-7F-07 R.C.C Lintel
    PLAS-7F-01 Wall Plaster - 7F
    PLAS-7F-02 Celing Plaster- 7F
    WRP-7F-02 Water proof coating to Wet areas
    WRP-7F-03 Vertical side w/p of wet area
    FLO-7F-11 Wet area -Ceramic Wall Clading
    FLO-7F-06 Wet area- Ceramic flooring
    FLO-7F-02 Floor Screed for Electrical Room
    FLO-7F-01 Ceramic tile to entrance loby
    FLO-7F-04 Skirting
    FLO-7F-03 Ceramic tile iside the room
    FLO-7F-05 Ceramic tiling to balconey and terrase
    FLO-7F-08 Marble flooring to coridoor
    FLO-7F-10 Corridor Wall Clading-Ceramic
    FLO-7F-07 Telephone room & other room flooring
    FLO-7F-09 Threshold
    FAL-7F-01 7F-Balcony False Ceiling
    FAL-7F-02 False Ceiling
    PANT-7F-01 Internal wall & ceiling painting
    PANT-7F-02 Final internal painting
    CARP-7F-01 Fixing of Door Frame
    CARP-7F-02 Fixing of Door Shutter
    CARP-7F-03 Fixing of Kitchen Cabinet
    CARP-7F-04 Fixing of Wardrobes
    MEP-7F-08 Bath Tub Fixing
    MEP-7F-12 Sanitary fixing & Mixer
    BLO-HC-01 cleaning
    BLO-HC-02 Block layout and checking
    BLO-HC-04 Internal Block Work
    BLO-HC-03 Block work -HC
    A0ON-HC-10 R.C.C Lintel - HC
    PLAS-HC-01 Wall Plaster - HC
    A0AS-HC-02 Celing Plaster- HC
    FLO-HC-07 rubber floor above screed in gym
    FLO-HC-09 rubber skirting
    FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)
    FLO-HC-11 swimming pool wall clading
    FLO-HC-14 Graniti Ceramic tile ( lift m/c room)
    WRP-HC-02 Water proof coating to Wet areas
    FLO-HC-02 White cement tiles
    WRP-HC-03 Vertical side w/p of wet area
    FLO-HC-04 wet area wall clading
    FLO-HC-05 Ceramic flooring to swiming pool wall
    A0LO-EX-02 Fixing of window sill
    FLO-HC-01 Floor Screed for Electrical / store / tel room
    FLO-HC-03 Marble flooring to lift loby
    FLO-HC-06 Threshold
    FLO-HC-08 Corridor Wall Clading-Ceramic
    FLO-HC-12 Ceramic flooring to Filter Room
    FLO-HC-13 Step to pool Deck
    PANT-HC-01 Lift Int .wall bitumen coating
    FAL-HC-01 False Ceiling
    PANT-HC-02 Internal wall & ceiling painting
    PANT-HC-03 Final internal painting
    PANT-HC-04 Epoxy painting to staircase
    CARP-HC-01 Fixing of Door Frame
    CARP-HC-02 Fixing of Door shutter
    MEP-HC-12 Sanitary fixing & Mixer
    BLO-UR-01 Block work-UR
    PLAS-UR-01 Wall Plaster- UR
    PLAS-UR-02 Celing Plaster- UR
    PLAS-UR-03 Staircase wall plaster
    PLAS-UR-04 Staircase Ceilling plaster
    CARP-UR-01 Fixing of Door Frame
    CARP-UR-02 Fixing of Door shutter
    MEP-B-02 MEP -Wall Conduites
    MEP-B-03 Fixing of DB Back box ,GI box
    MEP-B-04 Fixing of DB
    MEP-B-06 Internal wiring
    MEP-B-07 Main Cable work
    MEP-B-08 Switches & Sockets
    MEP-B-10 Instalation of Islolater for A/C
    MEP-B-09 Light Fittings
    MEP-GF-01 MEP -Wall Conduites
    MEP-GF-02 Fixing of DB Back box ,GI box
    MEP-GF-00 Fixing of DB
    MEP-GF-04 Internal wiring
    MEP-GF-06 Main Cable work
    MEP-GF-08 Switches & Sockets
    MEP-GF-10 Instalation of Islolater for A/C
    MEP-GF-09 Light Fittings
    MEP-1F-01 MEP -Wall Conduites
    MEP-1F-04 Fixing of DB Back box ,GI box
    MEP-1F-03 Fixing of DB
    MEP-1F-05 Internal wiring
    MEP-1F-07 Main Cable work
    MEP-1F-10 Switches & Sockets
    MEP-1F-12 Instalation of Islolater for A/C
    MEP-1F-11 Light Fittings
    MEP-2F-01 MEP -Wall Conduites
    MEP-2F-02 Fixing of DB Back box ,GI box
    MEP-2F-03 Fixing of DB
    MEP-2F-05 Internal wiring
    MEP-2F-07 Main Cable work
    MEP-2F-10 Switches & Sockets
    MEP-2F-12 Instalation of Islolater for A/C
    MEP-2F-11 Light Fittings
    MEP-3F-02 MEP -Wall Conduites
    MEP-3F-04 Fixing of DB Back box ,GI box
    MEP-3F-03 Fixing of DB
    MEP-3F-05 Internal wiring
    MEP-3F-07 Main Cable work
    MEP-3F-10 Switches & Sockets
    MEP-3F-12 Instalation of Islolater for A/C
    MEP-3F-11 Light Fittings
    MEP-4F-01 MEP -Wall Conduites
    MEP-4F-04 Fixing of DB Back box ,GI box
    MEP-4F-03 Fixing of DB
    MEP-4F-05 Internal wiring
    MEP-4F-07 Main Cable work
    MEP-4F-10 Switches & Sockets
    MEP-4F-15 Instalation of Islolater for A/C
    MEP-4F-14 Light Fittings
    MEP-5F-01 MEP -Wall Conduites
    MEP-5F-04 Fixing of DB Back box ,GI box
    MEP-5F-03 Fixing of DB
    MEP-5F-05 Internal wiring
    MEP-5F-07 Main Cable work
    MEP-5F-13 Switches & Sockets
    MEP-5F-15 Instalation of Islolater for A/C
    MEP-5F-14 Light Fittings
    MEP-6F-01 MEP -Wall Conduites
    MEP-6F-03 Fixing of DB Back box ,GI box
    MEP-6F-02 Fixing of DB
    MEP-6F-06 Internal wiring
    MEP-6F-07 Main Cable work
    MEP-6F-13 Switches & Sockets
    MEP-6F-15 Instalation of Islolater for A/C
    MEP-6F-14 Light Fittings
    MEP-7F-01 MEP -Wall Conduites
    MEP-7F-03 Fixing of DB Back box ,GI box
    MEP-7F-02 Fixing of DB
    MEP-7F-05 Internal wiring
    MEP-7F-07 Main Cable work
    MEP-7F-13 Switches & Sockets
    MEP-7F-14 Light Fittings
    MEP-7F-15 Instalation of Islolater for A/C
    MEP-HC-01 MEP -Wall Conduites
    MEP-HC-02 Fixing of DB
    MEP-HC-03 Fixing of DB Back box ,GI box
    MEP-UR-01 MEP Wall Conduites & instalation of DB Box
    MEP-HC-06 Internal wiring
    MEP-HC-08 Main Cable work
    MEP-HC-16 Switches & Sockets
    MEP-HC-17 Light Fittings
    MEP-HC-18 Instalation of Islolater for A/C
    MEP-B-01 Water supply PEX piping
    MEP-B-05 Water Supply PPR piping
    MEP-GF-03 Water supply PEX piping
    MEP-1F-02 Water supply PEX piping
    MEP-GF-05 Water Supply PPR piping
    MEP-2F-04 Water supply PEX piping
    MEP-3F-01 Water supply PEX piping
    MEP-1F-06 Water Supply PPR piping
    MEP-2F-06 Water Supply PPR piping
    MEP-4F-02 Water supply PEX piping
    MEP-3F-06 Water Supply PPR piping
    MEP-5F-02 Water supply PEX piping
    MEP-4F-06 Water Supply PPR piping
    MEP-6F-04 Water supply PEX piping
    MEP-5F-06 Water Supply PPR piping
    MEP-7F-04 Water supply PEX piping
    MEP-6F-05 Water Supply PPR piping
    MEP-HC-04 Water supply PEX piping
    MEP-7F-06 Water Supply PPR piping
    MEP-HC-05 Water Supply PPR piping
    MEP-HC-07 Above ground Drainage
    MEP-GF-11 Drainage Risers
    MEP-GF-12 Water supply Riser
    MEP-1F-13 Drainage Risers
    MEP-1F-14 Water supply Riser
    MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc
    MEP-2F-13 Drainage Risers
    MEP-2F-14 Water supply Riser
    MEP-3F-13 Drainage Risers
    MEP-3F-14 Water supply Riser
    MEP-GF-13 Water Heater fixing
    MEP-4F-11 Drainage Risers
    MEP-4F-12 Water supply Riser
    MEP-1F-15 Water Heater fixing
    MEP-2F-15 Water Heater fixing
    MEP-5F-10 Drainage Risers
    MEP-5F-11 Water supply Riser
    MEP-3F-15 Water Heater fixing
    MEP-6F-09 Drainage Risers
    MEP-6F-10 Water supply Riser
    MEP-4F-13 Water Heater fixing
    MEP-7F-09 Drainage Risers
    MEP-7F-10 Water supply Riser
    MEP-5F-12 Water Heter fixing
    MEP-HC-09 Water supply Riser
    MEP-HC-10 Drainage Risers
    MEP-6F-12 Water Heater fixing
    MEP-HC-13 Roof water supply work
    MEP-7F-11 Water Heter fixing
    MEP-HC-11 Water Heter fixing
    MEP-HC-14 Water tank Instlation
    MEP-HC-15 Pump Fitting
    A0VAC-B-17 Ducting work for A/C
    A0AC-GF-17 A/C unit hanging (indoor)
    A0AC-1F-18 A/C unit hanging (indoor)
    A0VAC-B-19 Ref. piping Work
    A0AC-GF-18 Ducting work for A/C
    A0AC-GF-20 Ref. piping Work
    A0AC-2F-18 A/C unit hanging (indoor)
    A0AC-3F-18 A/C unit hanging (indoor)
    A0AC-1F-19 Ducting work for A/C
    A0AC-1F-21 Ref. piping Work
    A0AC-2F-19 Ducting work for A/C
    A0AC-4F-18 A/C unit hanging (indoor)
    A0AC-2F-21 Ref. piping Work
    A0AC-GF-19 Ext.Fan Fixing
    A0AC-GF-21 Air out let fixing
    A0AC-3F-19 Ducting work for A/C
    A0VAC-B-16 Fresh air Duct
    A0AC-3F-21 Ref. piping Work
    A0AC-5F-18 A/C unit hanging (indoor)
    A0VAC-B-18 Ext.Fan Fixing
    A0VAC-B-20 Air out let fixing
    A0AC-4F-19 Ducting work for A/C
    A0AC-4F-21 Ref. piping Work
    A0AC-6F-18 A/C unit hanging (indoor)
    A0AC-2F-20 Ext.Fan Fixing
    A0AC-2F-22 Air out let fixing
    A0AC-1F-20 Ext.Fan Fixing
    A0AC-1F-22 Air out let fixing
    A0AC-5F-19 Ducting work for A/C
    A0AC-7F-18 A/C unit hanging (indoor)
    A0AC-3F-20 Ext.Fan Fixing
    A0AC-3F-22 Air out let fixing
    A0AC-6F-19 Ducting work for A/C
    A0AC-5F-21 Ref. piping Work
    A0AC-6F-21 Ref. piping Work
    A0AC-4F-20 Ext.Fan Fixing
    A0AC-4F-22 Air out let fixing
    A0AC-HC-20 A/C unit hanging (indoor)
    A0AC-7F-19 Ducting work for A/C
    A0AC-7F-21 Ref. piping Work
    A0AC-HC-21 Ducting work for A/C
    A0AC-5F-20 Ext.Fan Fixing
    A0AC-5F-22 Air out let fixing
    A0AC-6F-20 Ext.Fan Fixing
    A0AC-6F-22 Air out let fixing
    A0AC-HC-24 Ref. piping Work
    A0AC-HC-23 Ext.Fan Fixing
    A0AC-HC-25 Air out let fixing
    A0AC-7F-20 Ext.Fan Fixing
    A0AC-7F-22 Air out let fixing
    A0AC-HC-22 A/C units ( outdoor)
    WPR-1F-01 Balcony W/P 1F
    PAV-01 Precast Wheel Stopper
    WPR-2F-01 Balcony W/P 2F
    WPR-3F-01 Balcony W/P 3F
    WPR-4F-01 Balcony W/P 4F
    WRP-5F-01 Balcony W/P 5F
    WRP-6F-01 Balcony W/P 6F
    PLAS-EX-01 External roof area Plastering
    WRP-7F-01 Balcony W/P 7F
    PANT-EX-01 Epoxy painting to Roof
    PLAS-EX-02 Airwell Plastering
    PANT-EX-02 Epoxy painting to side of stair wall to S.Pool
    MET-06 Balconey Rainling
    PANT-EX-03 Fless Coat to Air Wall
    WRP-HC-01 waterproofing to swiming pool
    WRP-EX-01 Roof , Parapet wall W/P & Testing
    WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet
    WRP-EX-03 Bitumen coating to External Block Wall -A
    PLAS-EX-03 External elevation Plastering -A
    FLO-EX-01 External elevation marble wall clading-A
    MET-02 Aluminium Cladding On elevation- A
    MET-04 Aluminium Claading Upper Roof Area
    WRP-EX-04 Bitumen coating to External Block Wal- B
    PLAS-EX-04 External elevation Plastering -B
    FLO-EX-02 External elevation marble wall clading-B
    MET-03 Aluminium Cladding On elevation- B
    WRP-EX-05 Bitumen coating to External Block Wal-C
    PLAS-EX-05 External elevation Plastering -C
    FLO-EX-03 External elevation marble wall clading-C
    MET-07 Aluminium Cladding On elevation- C
    WRP-EX-06 Bitumen coating to External Block Wal-D
    PLAS-EX-06 External elevation Plastering -D
    FLO-EX-04 External elevation marble wall clading-D
    MET-08 Aluminium Cladding On elevation- D
    PAV-02 Fixing Kerb Stone at island & footh path
    PAV-03 Fixing 60mm Paving block
    PAV-04 80 mm Interlock at parking
    PAV-05 Trafic line marking
    A0MIS-03 Fixing of column guards
    MET-05 Aluminium / door & Window
    A0MIS-06 Compound Wall
    MET-09 Staircase Hand Rail
    MET-10 Cat ladders (For Airwel )
    MET-11 Steel Pipe Gaurde (basement water side)
    PR0-01 Security System
    PR0-05 Gate barriers
    PR0-03 Garbeg Disposal system
    PR0-02 Pool Work
    PRO-14 Reception counter
    PR0-08 Instaltion Of Generator
    PR0-09 TV system
    PR0-06 Fixing of lockers
    PR0-04 Sauna & Steam System
    PR0-07 Lift instalation & Commissioning
    PR0-11 Intercom system
    PR0-10 Cradle system instalation
    PR0-12 Transformar Instlation
    PR0-13 Music system
    TES-02 Testing & Commissioning
    TES-01 Signage
    TES-03 Civil Defance Inspection
    TES-04 DM Inspection
    TES-05 Complition certificate from DM
    TES-06 P R O J E C T H A N D O V E R
    SUCO-6F-15 Steel Work for 7.F Slab
    SUCO-6F-16 MEP sleves & conduits for 7.F Slab
    SUCO-6F-17 Seventh Floor Slab Casting (PART-B)
    SUCO-6F-18 Deshuttering PART- B
    SUCO-7F-01 steel work for column/A
    SUCO-7F-02 Form work for column/A
    SUCO-7F-03 Shear Wall /A
    SUCO-7F-04 Column casting For RF /A Slab
    SUCO-7F-05 Decking work for RF/A Slab
    SUCO-7F-06 Steel Work for RF/A Slab
    SUCO-7F-07 MEP sleves & conduits for RF/A Slab
    SUCO-7F-08 Roof Floor Slab Casting[Part-A ]
    SUCO-7F-09 Deshuttering PART- A
    SUCO-7F-11 steel work for column
    SUCO-7F-10 Shear Wall & Lift Core Wall
    SUCO-7F-12 Form work for column
    SUCO-7F-13 Column casting For RF Slab
    SUCO-7F-14 Decking Work for R.F Slab
    SUCO-7F-15 Steel Work for R.F Slab
    SUCO-7F-16 MEP sleves & conduits for R.F Slab
    SUCO-7F-17 Roof Slab Casting (PART-B)
    SUCO-7F-18 Deshuttering PART- B
    SUCO-HC-01 steel work for column
    SUCO-HC-02 Shear Wall & Lift Core Wall
    SUCO-HC-03 Form work for column
    SUCO-HC-05 Parapet Wall
    SUCO-HC-04 Column casting
    SUCO-HC-07 Swimming pool Shell
    SUCO-HC-10 Pool Deck
    SUCO-HC-06 Decking Work for HC Slab
    SUCO-HC-09 MEP sleves & conduits for HC Slab
    SUCO-HC-08 Steel Work for HC Slab
    SUCO-HC-11 Helth Club Slab Casting
    SUCO-HC-12 Deshuttering
    SUCO-UR-03 steel work for column
    SUCO-UR-02 Shear Wall & Lift Core Wall
    SUCO-UR-04 Form work for column
    SUCO-UR-05 Parapet Wall above HC
    SUCO-UR-01 Column casting For lift m/c room
    SUCO-UR-06 Decking Work for lift m/c room
    SUCO-UR-08 MEP sleves & conduits for lift m/c room
    SUCO-UR-07 Steel Work for lift m/c room
    SUCO-UR-09 Lift m/c room Slab
    BLO-B-01 cleaning
    BLO-B-02 Block layout and checking
    BLO-B-03 Block work in Basement
    BLO-B-04 R.C.C Lintel
    PLAS-B-01 Wall Plaster - Basement
    PLAS-B-02 Celing Plaster-Basement
    FLO-B-02 marble flooring to lift loby
    A0EXAV-09 Earth filling above raft 8’’tk
    FLO-B-04 Marble Wall Clading to Lift Loby
    FLO-B-05 4’’ PCC with mesh
    FLO-B-07 Pump/ Store room flooring
    FLO-B-01 Car parking /Driveway Floor Finishing
    FLO-B-03 floor finish to water tank area
    FLO-B-06 Wall clading to Pump room
    FLO-B-08 Thrishold
    FAL-B-01 False Ceiling
    PANT-B-01 Internal wall & ceiling painting
    PANT-B-02 Anticarbonation painting in wall
    PANT-B-03 Final internal painting
    CARP-B-01 Fixing of Door Frame
    CARP-B-02 Fixing of Door Shutter
    A0MIS-01 Substation Trenching Work
    MET-01 Aluminium (LOUVER WORK) Substation
    PANT-GF-01 Transformer room painting
    A0PRO-17 Dewa Inspection Substation
    A0PRO-18 Sub station hand over to DEWA
    BLO-GF-01 cleaning
    BLO-GF-02 Block layout and checking
    BLO-GF-03 Internal Block Work
    BLO-GF-04 Block work- GF
    A0ON-GF-08 R.C.C Lintel
    PLAS-GF-02 Celing Plaster- GF
    PLAS-GF-01 Wall Plaster GF
    WPR-GF-02 GF- Parking W/P
    WPR-GF-01 Water proof coating to Wet areas
    WPR-GF-03 Vertical side w/p of wet area
    FLO-GF-08 Wet area wall clading ( garbage room)
    FLO-GF-06 Wet area flooring (ceramic tiles)
    WPR-GF-04 Water proofing to substation slab roof
    FLO-GF-02 Floor Screed for Electrical Room/gym/
    FLO-GF-01 4’’ PCC with mesh
    FLO-GF-03 Floor Screed for M.hall
    FLO-GF-05 Floor Screed for Electricaal Sub-station
    FLO-GF-04 Car parking /Driveway Floor Finishing
    FLO-GF-07 Floor Screed for Gym / Shop
    FLO-GF-09 Mosaic flooring to stair floor & landing area
    FLO-GF-10 Floor Screed for Gen. Room
    FLO-GF-11 Store and other room flooring
    FLO-GF-12 mosaic step
    FLO-GF-14 Marble flooring to Entrance passage
    FLO-GF-15 mosaic skirting for steps
    FLO-GF-13 Threshold
    FLO-GF-17 Fixing Marble Steps
    FLO-GF-16 Marble Wall Clading to Lift Loby
    FAL-GF-01 False Ceiling
    PANT-GF-02 Internal wall & ceiling painting
    PANT-GF-03 Final internal painting
    PANT-GF-04 Anticarbonation painting in wall
    CARP-GF-01 Fixing of Door Frame
    CARP-GF-02 Fixing of Door Shutter
    CARP-GF-03 Fixing of Kitchen Cabinet
    CARP-GF-04 Fixing of Wardrobes
    MEP-GF-07 Sanitary fixing & Mixer
    BLO-1F-01 Cleaning
    BLO-1F-02 Block layout and checking
    BLO-1F-04 Block work- 1F
    BLO-1F-03 Internal Block Work
    A0ON-1F-07 R.C.C Lintel
    PLAS-1F-02 Celing Plaster- 1F
    PLAS-1F-01 Wall Plaster - 1F
    WPR-1F-02 Water proof coating to Wet areas
    WPR-1F-03 Vertical side w/p of wet area
    FL0-1F-10 Wet area -Ceramic Wall Clading
    FL0-1F-04 Wet area- Ceramic flooring
    FL0-1F-02 Floor Screed for Electrical Room
    FL0-1F-01 Ceramic flooring inside room
    FL0-1F-03 Ceramic tiling to balconey and terrase
    FL0-1F-05 Ceramic tile to entrance loby
    FL0-1F-06 Marble flooring to Corridor
    FL0-1F-07 Skirting
    FL0-1F-09 Corridor Wall Clading-Ceramic
    FL0-1F-08 Telephone room & other room flooring
    FL0-1F-11 Threshold
    FAL-1F-01 1F-Baalcony False Ceiling
    FAL-1F-02 False Ceiling
    PANT-1F-01 Internal wall & ceiling painting
    PANT-1F-02 Final internal painting
    CARP-1F-01 Fixing of Door Frame
    CARP-1F-02 Fixing of Door Shutter
    CARP-1F-03 Fixing of Kitchen Cabinet
    CARP-1F-04 Fixing of Wardrobes
    MEP-1F-08 Bath Tub Fixing
    MEP-1F-09 Sanitary fixing & Mixer
    BLO-2F-01 clening
    BLO-2F-02 Block layout and checking
    BLO-2F-04 Block work- 2F
    BLO-2F-03 Internal Block Work
    A0ON-2F-07 R.C.C Lintel
    PLAS-2F-01 Wall Plaster - 2F
    PLAS-2F-02 Celing Plaster- 2F
    WPR-2F-02 Water proof coating to Wet areas
    WPR-2F-03 Vertical side w/p of wet area
    FLO-2F-10 Wet area -Ceramic Wall Clading
    FLO-2F-05 Wet area- Ceramic flooring
    FLO-2F-01 Ceramic tile to entrance loby
    FLO-2F-02 Floor Screed for Electrical Room
    FLO-2F-03 Ceramic tile iside the room
    FLO-2F-04 Ceramic tiling to balconey and terrase
    FLO-2F-06 Marble flooring to Corridor
    FLO-2F-07 Skirting
    FLO-2F-09 Corridor Wall Clading-Ceramic
    FLO-2F-08 Telephone room & other room flooring
    FLO-2F-11 Threshold
    FAL-2F-01 2F-Baalcony False Ceiling
    FAL-2F-02 False Ceiling
    PANT-2F-01 Internal wall & ceiling painting
    PANT-2F-02 Final internal painting
    CARP-2F-01 Fixing of Door Frame
    CARP-2F-02 Fixing of Door Shutter
    CARP-2F-03 Fixing of Kitchen Cabinet
    CARP-2F-04 Fixing of Wardrobes
    MEP-2F-08 Bath Tub Fixing
    MEP-2F-09 Sanitary fixing & Mixer
    BLO-3F-01 cleaning
    BLO-3F-02 Block layout and checking
    BLO-3F-03 Block work -3F
    BLO-3F-04 Internal Block Work
    A0ON-3F-07 R.C.C Lintel
    PLAS-3F-01 Wall Plaster - 3F
    PLAS-3F-02 Celing Plaster- 3F
    WPR-3F-02 Water proof coating to Wet areas
    WPR-3F-03 Vertical side w/p of wet area
    FLO-3F-08 Wet area -Ceramic Wall Clading
    FLO-3F-03 Wet area- Ceramic flooring
    FLO-3F-01 Ceramic tiling to balconey and terrase
    FLO-3F-02 Ceramic tile iside the room
    FLO-3F-06 Floor Screed for Electrical Room
    FLO-3F-04 Ceramic tile to entrance loby
    FLO-3F-05 Skirting
    FLO-3F-07 Telephone room & other room flooring
    FLO-3F-09 Marble flooring to Corridor
    FLO-3F-10 Threshold
    FLO-3F-11 Corridor Wall Clading-Ceramic
    FAL-3F-01 3F-Baalcony False Ceiling
    FAL-3F-02 False Ceiling
    PANT-3F-01 Internal wall & ceiling painting
    PANT-3F-02 Final internal painting
    CARP-3F-01 Fixing of Door Frame
    CARP-3F-02 Fixing of Door Shutter
    CARP-3F-03 Fixing of Kitchen Cabinet
    CARP-3F-04 Fixing of Wardrobes
    MEP-3F-08 Bath Tub Fixing
    MEP-3F-09 Sanitary fixing & Mixer
    BLO-4F-01 cleaning
    BLO-4F-02 Block layout and checking
    BLO-4F-04 Block work -4F
    BLO-4F-03 Internal Block Work
    A0ON-4F-07 R.C.C Lintel
    PLAS-4F-01 Wall Plaster - 4F
    PLAS-4F-02 Celing Plaster- 4F
    WPR-4F-02 Water proof coating to Wet areas
    WPR-4F-03 Vertical side w/p of wet area
    FLO-4F-09 Wet area -Ceramic Wall Clading
    FLO-4F-08 Wet area- Ceramic flooring
    FLO-4F-02 Floor Screed for Electrical Room
    FLO-4F-01 Ceramic tile to entrance loby
    FLO-4F-03 Ceramic tiling to balconey and terrase
    FLO-4F-05 Marble flooring to Corridor
    FLO-4F-04 Ceramic tile iside the room
    FLO-4F-10 Telephone room & other room flooring
    FLO-4F-06 Corridor Wall Clading-Ceramic
    FLO-4F-07 Skirting
    FLO-4F-11 Threshold
    FAL-4F-01 4F-Balcony False Ceiling
    FAL-4F-02 False Ceiling
    PANT-4F-01 Internal wall & ceiling painting
    PANT-4F-02 Final internal painting
    CARP-4F-02 Fixing of Door Frame
    CARP-4F-03 Fixing of Door Shutter
    CARP-4F-01 Fixing of Kitchen Cabinet
    CARP-4F-04 Fixing of Wardrobes
    MEP-4F-08 Bath Tub Fixing
    MEP-4F-09 Sanitary fixing & Mixer
    BLO-5F-01 cleaning
    BLO-5F-02 Block layout and checking
    BLO-5F-04 Block work -5F
    BLO-5F-03 Internal Block Work
    A0ON-5F-07 R.C.C Lintel
    PLAS-5F-01 Wall Plaster - 5F
    PLAS-5F-02 Celing Plaster- 5F
    WRP-5F-02 Water proof coating to Wet areas
    WRP-5F-03 Vertical side w/p of wet area
    FLO-5F-10 Wet area -Ceramic Wall Clading
    FLO-5F-04 Wet area- Ceramic flooring
    FLO-5F-01 Floor Screed for Electrical Room
    FLO-5F-03 Ceramic tile to entrance loby
    FLO-5F-06 Marble flooring to Corridor
    FLO-5F-05 Ceramic tile iside the room
    FLO-5F-02 Ceramic tiling to balconey and terrase
    FLO-5F-08 Telephone room & other room flooring
    FLO-5F-07 Corridor Wall Clading-Ceramic
    FLO-5F-09 Skirting
    FLO-5F-11 Threshold
    FAL-5F-01 5F-Balcony False Ceiling
    FAL-5F-02 False Ceiling
    PANT-5F-01 Internal wall & ceiling painting
    PANT-5F-02 Final internal painting
    CARP-5F-02 Fixing of Door Frame
    CARP-5F-03 Fixing of Door Shutter
    CARP-5F-01 Fixing of Kitchen Cabinet
    CARP-5F-04 Fixing of Wardrobes
    MEP-5F-08 Bath Tub Fixing
    MEP-5F-09 Sanitary fixing & Mixer
    BLO-6F-01 cleaning
    BLO-6F-02 Block layout and checking
    BLO-6F-03 Block work -6F
    BLO-6F-04 Internal Block Work
    A0ON-6F-07 R.C.C Lintel
    PLAS-6F-01 Wall Plaster - 6F
    PLAS-6F-02 Celing Plaster- 6F
    WRP-6F-02 Water proof coating to Wet areas
    WRP-6F-03 Vertical side w/p of wet area
    FLO-6F-11 Wet area -Ceramic Wall Clading
    FLO-6F-05 Wet area- Ceramic flooring
    FLO-6F-01 Floor Screed for Electrical Room
    FLO-6F-03 Ceramic tile to entrance loby
    FLO-6F-04 Ceramic tile iside the room
    FLO-6F-02 Ceramic tiling to balconey and terrase
    FLO-6F-06 Skirting
    FLO-6F-09 Marble flooring to Corridor
    FLO-6F-10 Corridor Wall Clading-Ceramic
    FLO-6F-07 Telephone room & other room flooring
    FLO-6F-08 Threshold
    FAL-6F-01 6F-Balcony False Ceiling
    FAL-6F-02 False Ceiling
    PANT-6F-01 Internal wall & ceiling painting
    PANT-6F-02 Final internal painting
    CARP-6F-01 Fixing of Door Frame
    CARP-6F-02 Fixing of Door Shutter
    CARP-6F-03 Fixing of Kitchen Cabinet
    CARP-6F-04 Fixing of Wardrobes
    MEP-6F-08 Bath Tub Fixing
    MEP-6F-11 Sanitary fixing & Mixer
    BLO-7F-01 cleaning
    BLO-7F-02 Block layout and checking
    BLO-7F-03 Block work -7F
    BLO-7F-04 Internal Block Work
    A0ON-7F-07 R.C.C Lintel
    PLAS-7F-01 Wall Plaster - 7F
    PLAS-7F-02 Celing Plaster- 7F
    WRP-7F-02 Water proof coating to Wet areas
    WRP-7F-03 Vertical side w/p of wet area
    FLO-7F-11 Wet area -Ceramic Wall Clading
    FLO-7F-06 Wet area- Ceramic flooring
    FLO-7F-02 Floor Screed for Electrical Room
    FLO-7F-01 Ceramic tile to entrance loby
    FLO-7F-04 Skirting
    FLO-7F-03 Ceramic tile iside the room
    FLO-7F-05 Ceramic tiling to balconey and terrase
    FLO-7F-08 Marble flooring to coridoor
    FLO-7F-10 Corridor Wall Clading-Ceramic
    FLO-7F-07 Telephone room & other room flooring
    FLO-7F-09 Threshold
    FAL-7F-01 7F-Balcony False Ceiling
    FAL-7F-02 False Ceiling
    PANT-7F-01 Internal wall & ceiling painting
    PANT-7F-02 Final internal painting
    CARP-7F-01 Fixing of Door Frame
    CARP-7F-02 Fixing of Door Shutter
    CARP-7F-03 Fixing of Kitchen Cabinet
    CARP-7F-04 Fixing of Wardrobes
    MEP-7F-08 Bath Tub Fixing
    MEP-7F-12 Sanitary fixing & Mixer
    BLO-HC-01 cleaning
    BLO-HC-02 Block layout and checking
    BLO-HC-04 Internal Block Work
    BLO-HC-03 Block work -HC
    A0ON-HC-10 R.C.C Lintel - HC
    PLAS-HC-01 Wall Plaster - HC
    A0AS-HC-02 Celing Plaster- HC
    FLO-HC-07 rubber floor above screed in gym
    FLO-HC-09 rubber skirting
    FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)
    FLO-HC-11 swimming pool wall clading
    FLO-HC-14 Graniti Ceramic tile ( lift m/c room)
    WRP-HC-02 Water proof coating to Wet areas
    FLO-HC-02 White cement tiles
    WRP-HC-03 Vertical side w/p of wet area
    FLO-HC-04 wet area wall clading
    FLO-HC-05 Ceramic flooring to swiming pool wall
    A0LO-EX-02 Fixing of window sill
    FLO-HC-01 Floor Screed for Electrical / store / tel room
    FLO-HC-03 Marble flooring to lift loby
    FLO-HC-06 Threshold
    FLO-HC-08 Corridor Wall Clading-Ceramic
    FLO-HC-12 Ceramic flooring to Filter Room
    FLO-HC-13 Step to pool Deck
    PANT-HC-01 Lift Int .wall bitumen coating
    FAL-HC-01 False Ceiling
    PANT-HC-02 Internal wall & ceiling painting
    PANT-HC-03 Final internal painting
    PANT-HC-04 Epoxy painting to staircase
    CARP-HC-01 Fixing of Door Frame
    CARP-HC-02 Fixing of Door shutter
    MEP-HC-12 Sanitary fixing & Mixer
    BLO-UR-01 Block work-UR
    PLAS-UR-01 Wall Plaster- UR
    PLAS-UR-02 Celing Plaster- UR
    PLAS-UR-03 Staircase wall plaster
    PLAS-UR-04 Staircase Ceilling plaster
    CARP-UR-01 Fixing of Door Frame
    CARP-UR-02 Fixing of Door shutter
    MEP-B-02 MEP -Wall Conduites
    MEP-B-03 Fixing of DB Back box ,GI box
    MEP-B-04 Fixing of DB
    MEP-B-06 Internal wiring
    MEP-B-07 Main Cable work
    MEP-B-08 Switches & Sockets
    MEP-B-10 Instalation of Islolater for A/C
    MEP-B-09 Light Fittings
    MEP-GF-01 MEP -Wall Conduites
    MEP-GF-02 Fixing of DB Back box ,GI box
    MEP-GF-00 Fixing of DB
    MEP-GF-04 Internal wiring
    MEP-GF-06 Main Cable work
    MEP-GF-08 Switches & Sockets
    MEP-GF-10 Instalation of Islolater for A/C
    MEP-GF-09 Light Fittings
    MEP-1F-01 MEP -Wall Conduites
    MEP-1F-04 Fixing of DB Back box ,GI box
    MEP-1F-03 Fixing of DB
    MEP-1F-05 Internal wiring
    MEP-1F-07 Main Cable work
    MEP-1F-10 Switches & Sockets
    MEP-1F-12 Instalation of Islolater for A/C
    MEP-1F-11 Light Fittings
    MEP-2F-01 MEP -Wall Conduites
    MEP-2F-02 Fixing of DB Back box ,GI box
    MEP-2F-03 Fixing of DB
    MEP-2F-05 Internal wiring
    MEP-2F-07 Main Cable work
    MEP-2F-10 Switches & Sockets
    MEP-2F-12 Instalation of Islolater for A/C
    MEP-2F-11 Light Fittings
    MEP-3F-02 MEP -Wall Conduites
    MEP-3F-04 Fixing of DB Back box ,GI box
    MEP-3F-03 Fixing of DB
    MEP-3F-05 Internal wiring
    MEP-3F-07 Main Cable work
    MEP-3F-10 Switches & Sockets
    MEP-3F-12 Instalation of Islolater for A/C
    MEP-3F-11 Light Fittings
    MEP-4F-01 MEP -Wall Conduites
    MEP-4F-04 Fixing of DB Back box ,GI box
    MEP-4F-03 Fixing of DB
    MEP-4F-05 Internal wiring
    MEP-4F-07 Main Cable work
    MEP-4F-10 Switches & Sockets
    MEP-4F-15 Instalation of Islolater for A/C
    MEP-4F-14 Light Fittings
    MEP-5F-01 MEP -Wall Conduites
    MEP-5F-04 Fixing of DB Back box ,GI box
    MEP-5F-03 Fixing of DB
    MEP-5F-05 Internal wiring
    MEP-5F-07 Main Cable work
    MEP-5F-13 Switches & Sockets
    MEP-5F-15 Instalation of Islolater for A/C
    MEP-5F-14 Light Fittings
    MEP-6F-01 MEP -Wall Conduites
    MEP-6F-03 Fixing of DB Back box ,GI box
    MEP-6F-02 Fixing of DB
    MEP-6F-06 Internal wiring
    MEP-6F-07 Main Cable work
    MEP-6F-13 Switches & Sockets
    MEP-6F-15 Instalation of Islolater for A/C
    MEP-6F-14 Light Fittings
    MEP-7F-01 MEP -Wall Conduites
    MEP-7F-03 Fixing of DB Back box ,GI box
    MEP-7F-02 Fixing of DB
    MEP-7F-05 Internal wiring
    MEP-7F-07 Main Cable work
    MEP-7F-13 Switches & Sockets
    MEP-7F-14 Light Fittings
    MEP-7F-15 Instalation of Islolater for A/C
    MEP-HC-01 MEP -Wall Conduites
    MEP-HC-02 Fixing of DB
    MEP-HC-03 Fixing of DB Back box ,GI box
    MEP-UR-01 MEP Wall Conduites & instalation of DB Box
    MEP-HC-06 Internal wiring
    MEP-HC-08 Main Cable work
    MEP-HC-16 Switches & Sockets
    MEP-HC-17 Light Fittings
    MEP-HC-18 Instalation of Islolater for A/C
    MEP-B-01 Water supply PEX piping
    MEP-B-05 Water Supply PPR piping
    MEP-GF-03 Water supply PEX piping
    MEP-1F-02 Water supply PEX piping
    MEP-GF-05 Water Supply PPR piping
    MEP-2F-04 Water supply PEX piping
    MEP-3F-01 Water supply PEX piping
    MEP-1F-06 Water Supply PPR piping
    MEP-2F-06 Water Supply PPR piping
    MEP-4F-02 Water supply PEX piping
    MEP-3F-06 Water Supply PPR piping
    MEP-5F-02 Water supply PEX piping
    MEP-4F-06 Water Supply PPR piping
    MEP-6F-04 Water supply PEX piping
    MEP-5F-06 Water Supply PPR piping
    MEP-7F-04 Water supply PEX piping
    MEP-6F-05 Water Supply PPR piping
    MEP-HC-04 Water supply PEX piping
    MEP-7F-06 Water Supply PPR piping
    MEP-HC-05 Water Supply PPR piping
    MEP-HC-07 Above ground Drainage
    MEP-GF-11 Drainage Risers
    MEP-GF-12 Water supply Riser
    MEP-1F-13 Drainage Risers
    MEP-1F-14 Water supply Riser
    MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc
    MEP-2F-13 Drainage Risers
    MEP-2F-14 Water supply Riser
    MEP-3F-13 Drainage Risers
    MEP-3F-14 Water supply Riser
    MEP-GF-13 Water Heater fixing
    MEP-4F-11 Drainage Risers
    MEP-4F-12 Water supply Riser
    MEP-1F-15 Water Heater fixing
    MEP-2F-15 Water Heater fixing
    MEP-5F-10 Drainage Risers
    MEP-5F-11 Water supply Riser
    MEP-3F-15 Water Heater fixing
    MEP-6F-09 Drainage Risers
    MEP-6F-10 Water supply Riser
    MEP-4F-13 Water Heater fixing
    MEP-7F-09 Drainage Risers
    MEP-7F-10 Water supply Riser
    MEP-5F-12 Water Heter fixing
    MEP-HC-09 Water supply Riser
    MEP-HC-10 Drainage Risers
    MEP-6F-12 Water Heater fixing
    MEP-HC-13 Roof water supply work
    MEP-7F-11 Water Heter fixing
    MEP-HC-11 Water Heter fixing
    MEP-HC-14 Water tank Instlation
    MEP-HC-15 Pump Fitting
    A0VAC-B-17 Ducting work for A/C
    A0AC-GF-17 A/C unit hanging (indoor)
    A0AC-1F-18 A/C unit hanging (indoor)
    A0VAC-B-19 Ref. piping Work
    A0AC-GF-18 Ducting work for A/C
    A0AC-GF-20 Ref. piping Work
    A0AC-2F-18 A/C unit hanging (indoor)
    A0AC-3F-18 A/C unit hanging (indoor)
    A0AC-1F-19 Ducting work for A/C
    A0AC-1F-21 Ref. piping Work
    A0AC-2F-19 Ducting work for A/C
    A0AC-4F-18 A/C unit hanging (indoor)
    A0AC-2F-21 Ref. piping Work
    A0AC-GF-19 Ext.Fan Fixing
    A0AC-GF-21 Air out let fixing
    A0AC-3F-19 Ducting work for A/C
    A0VAC-B-16 Fresh air Duct
    A0AC-3F-21 Ref. piping Work
    A0AC-5F-18 A/C unit hanging (indoor)
    A0VAC-B-18 Ext.Fan Fixing
    A0VAC-B-20 Air out let fixing
    A0AC-4F-19 Ducting work for A/C
    A0AC-4F-21 Ref. piping Work
    A0AC-6F-18 A/C unit hanging (indoor)
    A0AC-2F-20 Ext.Fan Fixing
    A0AC-2F-22 Air out let fixing
    A0AC-1F-20 Ext.Fan Fixing
    A0AC-1F-22 Air out let fixing
    A0AC-5F-19 Ducting work for A/C
    A0AC-7F-18 A/C unit hanging (indoor)
    A0AC-3F-20 Ext.Fan Fixing
    A0AC-3F-22 Air out let fixing
    A0AC-6F-19 Ducting work for A/C
    A0AC-5F-21 Ref. piping Work
    A0AC-6F-21 Ref. piping Work
    A0AC-4F-20 Ext.Fan Fixing
    A0AC-4F-22 Air out let fixing
    A0AC-HC-20 A/C unit hanging (indoor)
    A0AC-7F-19 Ducting work for A/C
    A0AC-7F-21 Ref. piping Work
    A0AC-HC-21 Ducting work for A/C
    A0AC-5F-20 Ext.Fan Fixing
    A0AC-5F-22 Air out let fixing
    A0AC-6F-20 Ext.Fan Fixing
    A0AC-6F-22 Air out let fixing
    A0AC-HC-24 Ref. piping Work
    A0AC-HC-23 Ext.Fan Fixing
    A0AC-HC-25 Air out let fixing
    A0AC-7F-20 Ext.Fan Fixing
    A0AC-7F-22 Air out let fixing
    A0AC-HC-22 A/C units ( outdoor)
    WPR-1F-01 Balcony W/P 1F
    PAV-01 Precast Wheel Stopper
    WPR-2F-01 Balcony W/P 2F
    WPR-3F-01 Balcony W/P 3F
    WPR-4F-01 Balcony W/P 4F
    WRP-5F-01 Balcony W/P 5F
    WRP-6F-01 Balcony W/P 6F
    PLAS-EX-01 External roof area Plastering
    WRP-7F-01 Balcony W/P 7F
    PANT-EX-01 Epoxy painting to Roof
    PLAS-EX-02 Airwell Plastering
    PANT-EX-02 Epoxy painting to side of stair wall to S.Pool
    MET-06 Balconey Rainling
    PANT-EX-03 Fless Coat to Air Wall
    WRP-HC-01 waterproofing to swiming pool
    WRP-EX-01 Roof , Parapet wall W/P & Testing
    WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet
    WRP-EX-03 Bitumen coating to External Block Wall -A
    PLAS-EX-03 External elevation Plastering -A
    FLO-EX-01 External elevation marble wall clading-A
    MET-02 Aluminium Cladding On elevation- A
    MET-04 Aluminium Claading Upper Roof Area
    WRP-EX-04 Bitumen coating to External Block Wal- B
    PLAS-EX-04 External elevation Plastering -B
    FLO-EX-02 External elevation marble wall clading-B
    MET-03 Aluminium Cladding On elevation- B
    WRP-EX-05 Bitumen coating to External Block Wal-C
    PLAS-EX-05 External elevation Plastering -C
    FLO-EX-03 External elevation marble wall clading-C
    MET-07 Aluminium Cladding On elevation- C
    WRP-EX-06 Bitumen coating to External Block Wal-D
    PLAS-EX-06 External elevation Plastering -D
    FLO-EX-04 External elevation marble wall clading-D
    MET-08 Aluminium Cladding On elevation- D
    PAV-02 Fixing Kerb Stone at island & footh path
    PAV-03 Fixing 60mm Paving block
    PAV-04 80 mm Interlock at parking
    PAV-05 Trafic line marking
    A0MIS-03 Fixing of column guards
    MET-05 Aluminium / door & Window
    A0MIS-06 Compound Wall
    MET-09 Staircase Hand Rail
    MET-10 Cat ladders (For Airwel )
    MET-11 Steel Pipe Gaurde (basement water side)
    PR0-01 Security System
    PR0-05 Gate barriers
    PR0-03 Garbeg Disposal system
    PR0-02 Pool Work
    PRO-14 Reception counter
    PR0-08 Instaltion Of Generator
    PR0-09 TV system
    PR0-06 Fixing of lockers
    PR0-04 Sauna & Steam System
    PR0-07 Lift instalation & Commissioning
    PR0-11 Intercom system
    PR0-10 Cradle system instalation
    PR0-12 Transformar Instlation
    PR0-13 Music system
    TES-02 Testing & Commissioning
    TES-01 Signage
    TES-03 Civil Defance Inspection
    TES-04 DM Inspection
    TES-05 Complition certificate from DM
    TES-06 P R O J E C T H A N D O V E R