Templates for Highway Projects

Md Ariff Md ThayoobMember for 21 years 5 months
Created
3
5
0
Hi Memebers

Appreciate if you can spare me samples/templates on scheduling/programmong highway projects or websites where I can find them.

Regards

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear MD,

    Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs.

    The activities, sequence, resources, and duration, can be determined with the construction crews at site.

    But in general, you will have the followign divisions:
    I. Roads
    a. Excavation and Fill
    b. Subbase
    c. Basecourse
    d. Asphates
    II. Structures; buildings, bridges, culverts.
    a. Substructures
    b. Superstructures
    III. Electrical
    IV. Mechanical
    V. Signage

    If you have a more detailed question, please let us know.

    With kind regards,

    Samer
  2. 0
    Md Ariff Md Thayoob ·
    Thanks Samer
  3. 0
    Madhu Kumar ·

    Helo Everyone ,Can someone

    Helo Everyone ,

    Can someone help me how to implement "line of Balance" method in a highway project .