Sigmoid Curve
In the Open Standard
Wilfredo BarbacenaMember for 17 years 5 months
- Created
- 12
- 1
0
Hi,
I would greatly appreciate any comments.
The client submitted a schedule without any cost or resource loading and attached is an S-curve derived from excel via manual input of manpower distribution. This serve as the baseline progress curve as stated by them. To my clear understanding how did it ever happened or what is the relevance of generating an s-curve via manual input without any loading?
My concept in creating an s-curve is the basic approach, load the schedule. If ever if this wasn’t done then i suggested that they just use progress update from the baseline with the approved or consented date. Thus, S-curve shall be generated with more reliability and shall be presented in excel format.
I have also informed the client that in whatever delay in activity shall be borne by them without any implication from the owner due to non-loaded schedule.
Comments be it violent are welcome....
Willy
I would greatly appreciate any comments.
The client submitted a schedule without any cost or resource loading and attached is an S-curve derived from excel via manual input of manpower distribution. This serve as the baseline progress curve as stated by them. To my clear understanding how did it ever happened or what is the relevance of generating an s-curve via manual input without any loading?
My concept in creating an s-curve is the basic approach, load the schedule. If ever if this wasn’t done then i suggested that they just use progress update from the baseline with the approved or consented date. Thus, S-curve shall be generated with more reliability and shall be presented in excel format.
I have also informed the client that in whatever delay in activity shall be borne by them without any implication from the owner due to non-loaded schedule.
Comments be it violent are welcome....
Willy
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?