NEC CONTRACTS CALLING ALL PLANNERS

Brave GMember for 15 years 11 months
Created
3
3
0

I would appreciate it if all planners Could share their experience in applying NEC contracts in dispute. 

MEP

Building sevices

Rail

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Geoff I assume that you

    Hi Geoff

    I assume that you mean EoT disputes.

    The whole point of the NEC suite is that there should be no disputes if the contract has been administered correctly.

    You will have a problem if your side of the contract was in any way negligent in following the programming procedure.

    As far as I am aware there is very little case law on the topic - so why not google Atkinson Law and search their knowledge base.

    Best regards

    Mike T.

  2. 0
    Craig Ashley ·

    Can anyone enligten me on

    Can anyone enligten me on these issues please?

     

    When a contractor puts in a delay, that is down to the Client, are the effects of the delay based on the latest programme (and therefore the float at that time) or on the original baselined / contract programme and float?

     

    Further, when the Client receives an updated programme from the contractor (that shows slippage from the agreed Completion dates) if he doen't formally reject the programme is he accepting/agreeing to it?  That is to say, 'silence is acceptance?'

  3. 0
    Mike Testro ·

    Hi Craig You are in the wrong

    Hi Craig

    You are in the wrong forum.

    Re set your query in the Forensic claims section and then I will delete this one.

    Best regards

    Mike Testro