Qty / Manhour

Ronron MartinezMember for 16 years 10 months
Created
3
2
0

Hi All,

We got a new project and the client ask to prepare progress report and claim base on the manhours.

I think is not right cause the contract to them is lump sum re-measurement. I have proposed to them the progress report and claim base from installed qty, but they don't agree they still ask to submit manhours. any advise

Regards

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RonRon You can make a

    Hi RonRon

    You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure.

    It doesn't matter how accurate it is just so long as you use the same ratio for each report.

    My motto is "Give then what they want" but not necessarily how they want it.

    Best regards

    Mike Testro

  2. 0
    Ronron Martinez ·

    Hi Mike,If I make manhour as

    Hi Mike,

    If I make manhour as per the quantity I end up supplying a lot of workers.

    Cause the client estimated Manhour for every quantity is over allocate?

    Do you have construction activities man-hours?

    Regard

    Ron

  3. 0
    Gary Whitehead ·

    Why would you use the

    Why would you use the client's estimate of manhours instead of your own?

Log in or join to reply