Issues in calculate the projects completion%
In the Open Standard
Abdulaziz Bin EmranMember for 9 years 6 months
- Created
- 2
- 2
0
Hi
For example,
Project A have 2 Milestones start in 2017 and 2018
The work in milestone 1 is 100% complete , which is represent the major efoort og the whole project
milestone 2 is actually to do FQA
the point is the system we have consider all milestones as one weight which is not represent the reality.
* I can not use weghts formula because of top management order !
I need to came up with another soluation.