Primavera Pertmaster
In the Open Standard
JW
Jon WardMember for 18 years 4 months
- Created
- 10
- 5
0
Hello all,
i am (what i like to think of) a competant Planner,, i would really like to learn a lot about what Primavera Pertmaster can offer and the correct ways in which to use it,, does anyone know of a user guide or any free notes that may be able to help me,, strangley my employer didnt seem to keen to buy the software then let me learn.
thank you in advance
regards
jon
i am (what i like to think of) a competant Planner,, i would really like to learn a lot about what Primavera Pertmaster can offer and the correct ways in which to use it,, does anyone know of a user guide or any free notes that may be able to help me,, strangley my employer didnt seem to keen to buy the software then let me learn.
thank you in advance
regards
jon
10 replies
Oldest first- 0GHGuy Hindley ·I would agree with the previous response. Download a copy of Pertmaster from their web site. It lets you use the software with a restriction on number of activities and some functionality. This will give you a good idea of what the software is capable of doing - it is prety powerful.
In the UK Pertmaster run demonstrations of their software around the country - free of charge. I presume this happens elsewhere as well. Just look at their website for details.
Hope this helps. - 0PSPhil Shatz ·Hello!
We have just posted the free Pertmaster seminar schedule for the rest of the 2007 year at the following address:
http://www.primavera.com/events/seminars.asp
Here are the dates!
UK
August 28 Portsmouth
September 9 Bristol
September 11 Warrington
September 17 Aberdeen
September 23 Cambridge
September 30 Newcastle
October 2 Belfast
October 6 Dublin
October 8 London Docklands
October 9 Reading
October 15 Aberdeen
October 22 Norwich
November 4 Milton Keynes
November 11 Thurso
November 18 Derby
November 19 Aberdeen
November 25 London
December 9 Warrington
December 11 Bristol
Germany
September 17 Berlin
September 18 Hamburg
October 22 Dusseldorf
October 23 Frankfurt
October 28 Zurich
November 26 Stuttgart
November 26 Wien
November 27 Munchen
Feel free to let me have any questions on pshatz@primavera.com
Thx Phil - 0PSPhil Shatz ·Phil R,
Unfortunately those great whitepapers you wrote are not available on www.primavera.com.
The link for the Pertmaster information that is available
http://www.primavera.com/products/pertmaster/lit.asp
I would also recommend the case studies
http://www.primavera.com/products/pertmaster/stories.asp
Let me investigate if there is some way we can make these resources available on the Yahoo! user group. My understanding is that Planning Planet does not have a file store, correct?
Sorry, PhilS
---
Phil Shatz
Pertmaster Business Development
Guildford, Surrey - 0RGRoger Gibbs ·To all,
The white papers from Pertmaster, also the ones written by Philip R., can be found in the following links:
Integrated Cost/Schedule Risk Analysis using Risk Drivers & Cost Templates
(David Hulett, Hulett & Assoc.)
http://www.pertmaster.com/docs/whitepapers/IntegratedCostScheduleusingRiskDriversandCostTemplate.pdf
Using the Risk Register in Schedule Risk Analysis with Monte Carlo
Simulation (David Hulett, Hulett & Assoc & Waylon Whitehead,
ConocoPhillips)
http://www.pertmaster.com/docs/whitepapers/UsingRiskRegisterwithMonteCarlo_RiskFactorsVersion.pdf
Assessing Bid Viability in the Organization (Dan Patterson, PhD PMP
Pertmaster)
http://www.pertmaster.com/docs/whitepapers/AssessingBidViability.pdf
Schedule Risk Analysis Simplified (David Hulett, Hulett & Associates)
http://www.pertmaster.com/docs/whitepapers/riskanalysissimplified.pdf
Project Risk Management Procedures (Bob Harvey, CRT, Inc.)
http://www.pertmaster.com/docs/whitepapers/prmprocedures.pdf
Risk Management in Pharmaceutical R&D (Martin Powell, Indeco)
http://www.pertmaster.com/docs/whitepapers/RMinpharm.pdf
Importing Microsoft Project Schedules into Pertmaster (Stephen Cresswell,
Bombardier Transportation)
http://www.pertmaster.com/docs/whitepapers/ImportingMSschedules.pdf
Sensitivity Measures in Pertmaster 7.7 (Philip Rawlings, Euro log Ltd)
http://www.pertmaster.com/docs/whitepapers/sensitivitymeasures.pdf
Pertmaster Lags Clarified (Philip Rawlings, Euro log Ltd)
http://www.pertmaster.com/docs/whitepapers/lagsclarified.pdf Carryover
Modeling in Pertmaster (Philip Rawlings, Euro log Ltd)
http://www.pertmaster.com/docs/whitepapers/CarryoverModelling.pdf
Learning Curves in Pertmaster (Philip Rawlings, Euro log Ltd)
http://www.pertmaster.com/docs/whitepapers/learningcurves.pdf
Successfully Managing Contract Risk (Dan Patterson, PhD PMP Pertmaster)
http://www.pertmaster.com/docs/whitepapers/ContractRisk.pdf
Using Pertmaster within a Microsoft Project Environment (Dan Patterson, PhD
PMP Pertmaster)
http://www.pertmaster.com/docs/whitepapers/MSEnvironment.pdf
Controlling Cost Overruns (Dan Patterson, PhD PMP Pertmaster)
http://www.pertmaster.com/docs/whitepapers/CostOverruns.pdf
More Realistic Estimating: Separating Risks & Opportunities from
Uncertainty (Simon White, Pertmaster)
http://www.pertmaster.com/docs/whitepapers/RealisticEstimating.pdf
Benefits of Risk Assessment (Simon White, Pertmaster)
http://www.pertmaster.com/docs/whitepapers/BenefitsProjectRiskAssessment.pdf
Butler Report: Technology Audit on Pertmaster Risk Expert
http://www.pertmaster.com/docs/ButlerReportRiskExpert.pdf
Enhancing Project Schedule Credibility (John Zhao, Suncor Energy)
http://www.pertmaster.com/docs/whitepapers/Suncor_ProjScheduleCredibility.pdf
Cheers,
Roger