Some activities become open ended while importing xer file in Primavera Risk analysis

Sanam NegiMember for 14 years 1 month
Created
6
4
0

Hi every one,

 

I imported .xer file into primavera risk analysis, and while doing the schedule check I found out that there are some activities which became open-ended, whereas the activities are not open ended in primavera P6 "view log".

 

Please advise what could be the possible reason or how can i fix this.

 

 

Thanks

sanam

6 replies

Oldest first
  1. 0
    David Kelly ·

    Sanam, Start to Finish

    Sanam,

     

    Start to Finish relationships may not come accross

    If you have IT support, the PRA to P6 interface is MUCH better if you can read the P6 data directly into PRA and not through an XER file - but it is tricky to set up, ften needing IT help.

  2. 0
    Gary Whitehead ·

    Hi David, I'm very interested

    Hi David,

     

    I'm very interested to learn how you go about transferring P6 data directly into PRA instead of via an xer.

     

    I have some tame IT bods in my office who would probably be willing to give it a go. Could you give us a broad brush description of what is involved?

     

    Ta muchly,

     

    G

  3. 0
    David Kelly ·

    Gary,I have a pdf document?

    Gary,

    I have a pdf document? Not sure how to get it to you?

  4. 0
    Sanam Negi ·

    Hi david, I tried it but

    Hi david,

     

    I tried it but there was some error and i could not find the fix for it. could you please send me the PDF for the error correction or simple steps to do it.

     

    Sanam

  5. 0
    Gary Whitehead ·

    David, I've Private Message'd

    David,

     

    I've Private Message'd you with my email adress.

     

    Cheers,

     

    G

  6. 0
    David Kelly ·

    Gary, Didn't get it.....

    Gary,

     

    Didn't get it..... 

Log in or join to reply