Using pertmaster to assess cost savings
In the Open Standard
Neil BradyMember for 19 years 9 months
- Created
- 3
- 3
0
I have been asked to model some cost savings, and I am struggling to think about how to model the answers, so was wondering if anyone could help.
For example
Cost Saving
Cost Saving 1
£974,000 min
£1,640,000 mean
£1,949,000 max
Cost Saving 2
£880,000 min
£880,000 mean
£1,208,000 max
Cost Saving 3
£546,000 min
£780,000mean
£819,000 max
How would I go about modelling this? I am thinking its almost the opposite of a normal simple cost risk as really you want the probability of a potential extra saving.
Does this mean that I should input them as negative costs?
Struggling with this one, as if I plug it in as normal I get a 99% chance of 3300000, P80 of say 3000000 as an example, which is kind of meaningless ? I have a 99% chance of reaching my saving, when really I need to know what the chances are of saving more (Or less)
Any help you can give as always greatly appreciated!!!!
For example
Cost Saving
Cost Saving 1
£974,000 min
£1,640,000 mean
£1,949,000 max
Cost Saving 2
£880,000 min
£880,000 mean
£1,208,000 max
Cost Saving 3
£546,000 min
£780,000mean
£819,000 max
How would I go about modelling this? I am thinking its almost the opposite of a normal simple cost risk as really you want the probability of a potential extra saving.
Does this mean that I should input them as negative costs?
Struggling with this one, as if I plug it in as normal I get a 99% chance of 3300000, P80 of say 3000000 as an example, which is kind of meaningless ? I have a 99% chance of reaching my saving, when really I need to know what the chances are of saving more (Or less)
Any help you can give as always greatly appreciated!!!!
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?