Looking for Decent Risk Software

Jay SMember for 18 years 5 months
Created
1
29
0

I am looking for Decent Risk Software

 

I have the following requirements

 

1) Integrateable with Primavera and MS project

2) Easy to use

3) Consider Lags and Logic as part of the Risk Assesment. (Example) Optimistic Logic FS-10D /  Pesimistic = FS +5D / and FS

 

 

1 reply

Oldest first
  1. 0
    Vladimir Liberzon ·

    Spider Project includes risk

    Spider Project includes risk simulation that considers different logic and conditional links, exports/imports schedules to MS Project and Primavera if necessary, but is much more functional and powerful than both of them.

    Try Demo downloading from www.spiderproject.ru, look at the publications on Success Driven Project Management at the same site.