multiple activities affected by a single risk

Mark HigginsMember for 9 years 8 months
Created
2
4
0

Good evening,

I have been approached by a PM that I support who has asked a question of which i am unsure how to answer.

The question is about applying a single risk against multiple schedule activities

would the best approach be to breakdown the over arching risk into smaller multiple risks, and apply individual probability and 3 point estimate values on a task by task basis.

The risk is based around Human Resource availability

 

any assistance would be greatly received

 

Cheers

Mark

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Mark - Welcome to Planning

    Hi Mark - Welcome to Planning Planet

    There are many types of risk that affect multiple tasks - weather is typicle.

    If there is likely to be a shortgae of labour then put a cap on the number expected to be deployed and the end date will extend accordingly.

    Best regards

    Mike Testro

  2. 0
    Rafael Davila ·

    Definitively resource

    Definitively resource availability might not be deterministic, this is an excellent question.

    If using Spider Project I would suggest using the 3 scenarios approach to model different resource availability profiles [optimistic, pessimistic and probable] using Time or Activity resource production. 

     photo 3scenarios_zps4i9xzjdu.jpg

    This method does not have many of the limitations Monte Carlo models do have and can be implemented using your CPM software without the need for specialized Risk software.

    http://www.spiderproject.com/images/img/pdf/Methods%20and%20Tools%20of%20Success%20Driven%20Project%20Management.pdf

    The following SPERT Excel Templates might help you get the distribution curves, with little modification you can get the cumulative % distributions.  Statistical PERT Normal Edition uses ratio scale multipliers to modify the standard deviation of a normal curve. This lets Statistical PERT work with any bell-shaped uncertainty that can be estimated using a 3-point estimate for minimum, maximum and most likely outcomes.

    https://www.statisticalpert.com/download-free-templates/#duration

     photo CumS01_zpsel6afgpl.jpg

     photo CumS03_zpsdm3w7nmt.jpg