Hi Guys,

I want to know your opinion about the workload´s difference   in the monitoring   of Planning  type  shutdown   compared  with EPC Planning.

 How oft in minimum must  a shutdown planning  be updated ?

Thanks

Kamel

1 reply

Oldest first
  1. 0
    Bernard Ertl ·

    Schedules for

    Schedules for Shutdowns/Turnarounds/Outages should be updated at the end of every shift.  Management should have updated progress reports and field supervisors should have updated shift (or "look ahead") schedules before the start of the next shift.