M2.4 Progress Updating & Schedule Control
Knowledge
Articles and chapters
- M3.3 — Commitments, Actuals & Accruals21 Oct 2026
By the end of this section, the learner should be able to establish and explain a reliable period-end cost position by reconciling recognised actual cost, open commitments and costs incurred but not yet recorded. They should be able to define an appropriate financial cut-off and validate and integrate data sources.
- M2.4 — Progress Updating & Schedule Control21 Oct 2026
1. Practical outcomeBy the end of this section, the learner should be able to take an approved schedule and turn it into a trustworthy current control model at each reporting cycle. They should be able to establish a clear data date, collect and validate actual progress, record actual starts and acomplishments.
- M2.2 — Logic, Critical Path & Float21 Oct 2026
The learner should be able to construct and analyse a logically linked schedule, choose relationships, recognise missing or inappropriate logic, distinguish logic from constraints, identify critical and near-critical paths, understand total and free float, recognise negative or unusually high float.
- M1.4 — Progress Measurement21 Oct 2026
By the end of this section, the learner should be able to design, apply and challenge progress-measurement rules that convert evidence of completed work into a credible statement of physical accomplishment. They should be able to choose an appropriate measurement method.
- M2 — Planning & Scheduling21 Oct 2026
Module 2 establishes the essential practices for developing, managing and controlling credible project schedules. It explains how to translate project scope into a structured schedule, establish logical relationships, identify critical and near-critical paths, and understand float and milestone dependencies. It also covers how to assess resource availability, productivity and delivery constraints, optimise schedules, and maintain accurate progress updates using objective evidence. Finally, it explains how to analyse schedule performance, forecast likely completion dates, identify emerging risks and evaluate recovery options. Together, these practices provide a reliable foundation for understanding project timelines, monitoring delivery performance, anticipating delays and supporting informed decisions to keep projects on track.
- 19 May 2012
- Progress Recording20 Apr 2009
Progress Recording... There are various ways to record progress on schedules or for schedules but the most efficient way would be using pdf print outs & saving electronic versions of the pdf copies for back up in a separate folder. You must be disciplined & consistently efficient in recording the da
- Progress Update8 Mar 2009
Schedules are only useful if they are updated in a timely manner. Most project schedules must be statused and updated monthly. Some complex construction projects or jobs that have a very dynamic schedule should be statused more frequently. The [[earned value]] management plan must establish clear an
- Schedule Maintenance7 Mar 2009
Schedule Maintenance related issues:
Discussions
25 discussions
- 4repliesReviewing a contractor's monthly P6 update: what do you check first?DiscussionOracle Primavera - PM6by Bilingualpmo· 2 weeks ago
- 11repliesCalculated time vs durationShutdowns / Turnarounds / Outages (STOs)by Floris Gering· 1 year ago
- 1replyHow many shutdown planners should I have?Shutdowns / Turnarounds / Outages (STOs)by Aaron Morris· 7 years ago
- 0repliesUsing ScheduleReader in STOs?Shutdowns / Turnarounds / Outages (STOs)by Joel Roberts· 7 years ago
- 15repliesTurnaround schedule levelsShutdowns / Turnarounds / Outages (STOs)by Floris Gering· 7 years ago
- 17repliesResource Linking - good/bad?Shutdowns / Turnarounds / Outages (STOs)by Mark Chapman· 8 years ago
- 4repliesControlling discovery & extra workShutdowns / Turnarounds / Outages (STOs)by Floris Gering· 10 years ago
- 0repliesRegular Maintenance vs. Turnaround Maintenance CostShutdowns / Turnarounds / Outages (STOs)by Kosmo Lisowski· 10 years ago
- 0repliesResource dependent activitiesTURNAROUND & SHUTDOWN (T/A & S/D)by Frank A· 10 years ago
- 2repliesdeShutdowns / Turnarounds / Outages (STOs)by Onur Dag· 10 years ago
1–10 of 25
Blogs
Thought leadership
- PROCEDURES No 15 – Planning Standards10 Aug 2026
Fed up with adverts from software companies and consultancies that are going to change the world of Planning and solve all your project problems? This series of occasional articles promises nothing but thought provoking questions on how well we understand the basics of our profession from the…
PP Admin
Jobs
Roles asking for this
- United Kingdom (EU.UK)Contract or PermanentCivil / Building / E&MSalary: £50,000–£75,000
Norms & Rates
Rates, norms and durations
No norms tagged yet
Rates, norms and durations appear here once entries are linked to this subject.
Resources
Papers, standards and tools
No resources yet
Summaries of papers, standards and tools are added by editors and appear here once published.