Example in turnarounds for 4 basic relationships.

Floris GeringMember for 12 years 2 months
Created
5
7
0

Hi guys,

I'm new to the scheduling world (coming from a computer science track) now working as a consultant.

As I understand it there are 4 basic relationships between activities and they are central to the concept of network analysis.

1) FS finish to start

2) FF finish to finish

3) SS start to start

4) SF start to start.

 

Number 4 is especially difficult to grasp for me, in a practical sense.

Could someone please explain these 4 relationships with commonly used activities in a turnaround ?

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi FlorisThe simple answer is

    Hi Floris

    The simple answer is only use FS links in any form of programming.

    Best regards

    Mike Testro

  2. 0
    Floris Gering ·

    Why ?Why are there 3 other

    Why ?

    Why are there 3 other types (which also make sense, except the Start to finish for my understanding ?) when only the Finish Start relation could deal with everything ?

  3. 0
    Vladimir Liberzon ·

    Floris,I don't recommend to

    Floris,

    I don't recommend to use SF relationship. In most cases it is used by an error. Other three reflect real life constraints and may be used. But usually SS+Lag shall be used together with FF+Lag, if an activity can start after another activity it usually shall not finish before succeding activity. So both dependencies shall be used in parallel.

  4. 0
    Mike Testro ·

    Hi FlorisThis forum is

    Hi Floris

    This forum is predominantly used by construction professionals.

    You have to remember that the people who develop programming software are geeks not builders.

    Programming software is used for many industries as well as construction but the programmers are not pharmacists or industrialists either.

    In manufacturing for instance with a production flow line the SS plus lag combined with FF creates a "ladder" chart which replicates the production method.

    This method has no place in construction although my sparring partner Vladimir will disagree when planning linear projects such as pipelines.

    The fact that a SF link is available is an example of the software writers complete ignorance of practical usage - at least Vladimir and I agree on that point.

    Best regards

    Mike Testro

  5. 0
    Thomas Hinckley ·

    FS should be your most used

    FS should be your most used relationship.  You should never use SF relationships.  In my opinion they should be removed from the program. 

    SS and FF are useful in certain circumstances but especially in a TAR schedule will be very limited. 