Calculated time vs duration
- Created
- 11
- 91
I have for example a safety valve which has to be replaced and calculated the disassembly and assembly time for example to be 2 hours.
My colleague scheduler says he always sets the duration for this activity to 10 hours (in this case the length of a shift), because he is only interested in the fact that the work on the safety valve is done on a specific day during this shift and not exactly in which 2 hours it is done.
Is this good practice ? Why ? (or why not)
11 replies
Oldest first- 0VLVladimir Liberzon ·
No, it is not best
No, it is not best practice.
Best practice includes assigning resources to project activities and calculation of resource constrained schedule based on volumes of work to be done and assigned resource productivities. Activity duration shall be calculated and resources optimized.
Activity duration does not depend on assigned resources only for few activity types.
Duration based schedules may be used only if the job will be done by someone else and the schedule is used for contract execution analysis.
Shutdown projects are usually planned at least in hours (better in minutes) because delays cost a lot. Good schedule optimizes resource usage and minimizes project duration.
- 0SASteven Auld ·
Floris,I agree with Vladimir,
Floris,
I agree with Vladimir, each activities duration should be based on how long it is estimated to take.
If you allocate 10 hours to 1 safety valve that takes only 2 hours to complete, then the Resource availability will no longer show as available for other activities.
If you have 5 safety valves to overhaul then by allocating only the required 2 hours per safety valve, then all could be completed within a 10 hour shift.
If you have allocated 10 hours then this would mean that you would not show sufficient resource availability & would drive the duration out to 5 shifts to complete this scope of work.
In the shutdown plans that I work on, resource availability is the single critical driver for the shutdown duration due to limited bed space availability. To incorrectly allocate durations would have a significant impact on the overall shutdown duration & would also reduce the amount of work that could be completed wihtin the Critical Path duration.
Regards,
Steven
- 0ZPZoltan Palffy ·
if the planning units is in
if the planning units is in hours then show the 2 hours because if you show 10 hours as others have stated it will over alloate the resource and it will also prevent follwo on work from starting sooner.
bad practice
replace safety valve #1 - 10 hours-----> replace safery valves #2 - 10 hours = total 20 hours 2 valves replaced
good practice
replace safety valve #1 - 2 hours-----> replace safert valves #2 - 2 hours -------> replace safety valve #3 - 2 hours----->
replace safety valve #4 - 2 hours-----> replace safert valves #5 - 2 hours -------> = total 10 hours 5 valves replaced
now if your planning unit was days then the smallest unit of time that you can plan for is 1 day regarless if it takes 2 hours or 10 hours to do it is still 1 day.
- 0FGFloris Gering ·
Thanks for these insights.I'm
Thanks for these insights.
I'm still confused:
Let me try to describe my problem with understanding this for most people "easy question":
Basic data:
Calender: Mon-Sat, 06:00-16:00 so 10 hours.
5 Safetyvalves to be replaced, each calculated within a normset to 2 hours, so budgeted units in P6 = 2. With 1 Budgeted Unit/Time we get a Original Duration of 2 hours per SV.
I'm not interested in a specific sequence of the replacement of these 5 valves, so there should be no logical ties between the 5 of them, correct ?
I AM interested in getting this replacement of all 5 of them done in one shift, lets say the Monday., by 1 worker.
What is the best approach to schedule this and why ?
- 0VLVladimir Liberzon ·
Include in your schedule a
Include in your schedule a milestone with the special calendar - can happen only on Monday before the start of the regular work day.
Set FS dependnecies from this milestone to all five valve replacement activities.
If you have only one worker that can do this work resource leveling will schedule all these activities on Monday one after another if other dependencies do not prevent this.
- 0FGFloris Gering ·
Thanks, I think I understand
Thanks, I think I understand it.
A specific turnaround question:
Mechanical work is often calculated with unit rates as a normset, so for instance replacement of a DN25 Safetyvalve would take about 1,5hours. These units are transferred to Primavera and land in the Budgeted Units for the mechanical worker for this activity. When the units/time are 1, the duration would be 1,5hours. So starting at 6 o'clock in the morning would lead to a finish time of 07:30.
Colleague schedulers are divided into 2 camps:
1) check all durations for mechanical work and round to fixed size duration blocks. For instance: 2h, 4h, 8h, 10h. When they habe done this as a result there are only nice and even rounded durations for the mechanical work in the schedule.
2) leave durations initially as they are, when you think it can be executed faster or slower, change the duration of the mechanical activity accordingly.
I'm in number 2). Thinking about successors version 1) would artifically build float at activity level in your schedule, because the succesor when usually related by a FS-relationship, will start after the extended duration mechanical activity will end.
What would you say is the best way to look at this problem of rounding durations of mechanical work ? 1 or 2 ?
- 0FGFloris Gering ·
Sorry, I,m still confused.
Sorry, I,m still confused. Maybe I can elaborate one more time with a bit more detail to showcase my problem in understanding.
All our mechanical work in our turnaround is done by 1 contractor. Assume we work in the early shift 10 hours, with 8 workers.
Mechanical work is calculated, based on a unit rate, so in general the amount of budgeted units and therefore the duration are not rounded numbers. (1,13 hours, 4.65 hours, 8,14 hours, etc)
After importing these workpackages from (Roser in our case) to P6, the first thing some of my colleauges do, is rounding al these durations to blocks of 4hours, 8hours etc.
Valve exchange example:
Original values: 1) PCT disconnect 0,5 hours -> 2) exchange valve DN.... 2,84 hours (unit rate example) -> PCT connect 0,5 hours.
After rounding: 1) PCT disconnect 4 hours -> 2) exchange valve DN.... 4 hours (unit rate example) -> PCT connect 4 hours.
In all cases Budgeted Units/Time are originally 1, so the durations are equal to the budgeted units.
After rounding the durations up, not changing the budgeted units, Primavera would lower the budgeted units/time, because you artificially stretch the work in my opinion.
So the question is: what is the way to go with unit rate based calculations in work packages in a turnaround setting ? The people who round everything say it is much easier to level resource hours per day and this reflects reality more than using the original not-rounded data. I'm not convinced. Aren't they adding artifical free float on basic activity level ?
- 0FGFloris Gering ·
Sorry, I,m still confused.
Sorry, I,m still confused. Maybe I can elaborate one more time with a bit more detail to showcase my problem in understanding.
All our mechanical work in our turnaround is done by 1 contractor. Assume we work in the early shift 10 hours, with 8 workers.
Mechanical work is calculated, based on a unit rate, so in general the amount of budgeted units and therefore the duration are not rounded numbers. (1,13 hours, 4.65 hours, 8,14 hours, etc)
After importing these workpackages from (Roser in our case) to P6, the first thing some of my colleauges do, is rounding al these durations to blocks of 4hours, 8hours etc.
Valve exchange example:
Original values: 1) PCT disconnect 0,5 hours -> 2) exchange valve DN.... 2,84 hours (unit rate example) -> PCT connect 0,5 hours.
After rounding: 1) PCT disconnect 4 hours -> 2) exchange valve DN.... 4 hours (unit rate example) -> PCT connect 4 hours.
In all cases Budgeted Units/Time are originally 1, so the durations are equal to the budgeted units.
After rounding the durations up, not changing the budgeted units, Primavera would lower the budgeted units/time, because you artificially stretch the work in my opinion.
So the question is: what is the way to go with unit rate based calculations in work packages in a turnaround setting ? The people who round everything say it is much easier to level resource hours per day and this reflects reality more than using the original not-rounded data. I'm not convinced. Aren't they adding artifical free float on basic activity level ?
- 0RDRafael Davila ·
Too easy, why not?The
Too easy, why not?
- The replacement of 15 valves with no logical ties between them.
- The replacement of 5 of them done in one Monday shift, in batches of five by 1 worker, the 15 will take 3 Mondays.
Essentially same rule, to replace in batches of 5 but 15 valves, not a big deal, easy if using consumable resources leveling for the milestones.
More interesting is the following.
Good Luck
- 0EAEmerald Associates APAC ·
Hi All, An innovative product
Hi All,An innovative product line of Oracle Primavera enhancements and add-ons unique to Emerald Associates. Our clients come to us with Primavera problems, and we create tools to solve them.Emerald Tools - Primavera Enhancements and Add-OnsYou may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk
- 0EAEmerald Associates APAC ·
Hi All, An innovative product
Hi All,An innovative product line of Oracle Primavera enhancements and add-ons unique to Emerald Associates. Our clients come to us with Primavera problems, and we create tools to solve them.Emerald Tools - Primavera Enhancements and Add-OnsYou may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?