Field work vs office work
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 1
- 2
0
Field work is paid for each turn of work. First 8 hours are paid at $100 each, the following 2 are paid $150 and the following hour is paid $200.
A person who worked 8 hours in a turn earns $800, a person who worked 11 hours in a turn earns $800 + $300 + $200 = $1500
A person working in the office earns 2000 not caring if he worked 8 or 11 hours.
Each one is paid the friday each 2 weeks.
How can I model this in Spider?
A person who worked 8 hours in a turn earns $800, a person who worked 11 hours in a turn earns $800 + $300 + $200 = $1500
A person working in the office earns 2000 not caring if he worked 8 or 11 hours.
Each one is paid the friday each 2 weeks.
How can I model this in Spider?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?