Skip to content

Resource constrained schedule does not seem to work for SF links

Evgeny Z.Member for 18 years 9 months
Created
24
9
0

Dear all,

Can you please check the below example.

Unless I am missing something it looks for me, that Resource Constrained Schedule does not produce correct results for Start to Finish linked tasks.

See example below

Initial schedule

 photo SF_links001_01_initial_zps93e6cba4.png

Resource Contrained scheduled

 photo SF_links001_02_resourceconstrained_zpsdaa92193.png

What I think Resource Constrained Schedule shall produce

 photo SF_links001_03_resourceconstrained_should_be_zpsa15aa23d.png

Regards.

 

Evgney

24 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Evgeny,activity 4 shall

    Evgeny,

    activity 4 shall finish after activity 3 start. In the last screenshot it finishes before activity 3 start.

    I tried to create your project and got the following schedule that looks right:

     photo SF_zpsde16b6fb.jpg

  2. 0
    Mike Testro ·

    Hi EvgenyVlaimir was too

    Hi Evgeny

    Vlaimir was too kind.

    The type of link that you described - Start to Finish - has no place in construction planning so stop doing it now.

    Best regards

    Mike Testro

  3. 0
    Vladimir Liberzon ·

    Mike,sometimes we use this

    Mike,

    sometimes we use this link to hammocks but I don't remember a single case when we used this dependency for real activities.

  4. 0
    Rafael Davila ·

    Mike,Never say never .... we

    Mike,

    Never say never .... we have such activities in all our jobs, our crime rate is high.

    If the owner delays bringing his security as it happens on government jobs then the start of his activity will delay the finish of ours. 

     photo nsn00236_zpse11e5b75.jpg

    Not surprisingly I don't remember a single other case when we used this dependency for real activities, but maybe I used them, just do not recall,... never say never.

    So on a forensic analysis if the owner delays the start of his responsibilities he would not be liable for delaying the finish of my responsibilities with regard to site security?

    Best Regards,

    Rafael

  5. 0
    Vladimir Liberzon ·

    Rafael,Contractor site

    Rafael,

    Contractor site security is a hammock (LOE) activity that may finish as soon as owner site securuty starts.

  6. 0
    Evgeny Z. ·

    Gentlemen,in Microsoft

    Gentlemen,

    in Microsoft Project I normally use Start to Finish relation to plan "just in time" delivery. This is actually what it is meant for, as I understand:

    http://office.microsoft.com/en-gb/project-help/linking-project-tasks-RZ001135937.aspx?section=8

    In the example of my 1st post, I need Activity 4 to finish just before Activity 2.

    Spider schedules it correctly for non-resource constrained schedule, however when resources are constrained, Activity 4 gets delayed, and this is clearly not what I want. In case of constrained resources, I want it to be brought forward. The real life logic is as follows: if we can't do it just in time, let us do it a bit earlier.

    So, now I have the following questions

    1) What is the purpose of the SF relation in Spider if, when resources leveled, it does no obey the logic, imposed by non-resourced leveled schedule?   For me it looks that without resource-leveling is follows the SF logic, however with resource leveling it follows Start to Start logic.

    2) If not using SF logic, how would I achieve correctly resource-leveled just in time delivery planning?

     

    Regards.

    Evgeny

    PS.

    1. Vladimir, there was a Resource A, assigned to Activity 3 in my example, that is why we got different results.
    2. Microsoft Project also resource-levels it not the way I would expect
  7. 0
    Vladimir Liberzon ·

    Evgeny,in your screenshots

    Evgeny,

    in your screenshots you did not show that resource A is assigned to activity 3. In this case the schedule that you presented is correct.

    I want to remind you that FS, SS, FF, and SF dependencies are of No Earlier Than type. It means that if you apply SF dependency succeding activity shall finish AFTER preceeding activity start. So using SF dependencies for JIT modeling is totally wrong. With resource leveling succeding activity may be delayed and it will be right!

    For this purpose link activities with FS dependency (in right order), make preceding activity ALAP (select this in activity properties) and you will get required result.

    Don't do this with MS Project - it interprets ALAP different way delaying all successing activities.

  8. 0
    Evgeny Z. ·

    Vladimir,thank you very much

    Vladimir,

    thank you very much for your answer.

    In Spider setting activities, which are to be "just in time delivered" to be ALAP worked fine. Also resource leveling worked correctly in this case.

    In Microsoft Project, as you pointed out, it pushed all succession activities backwards. So in Microsoft Project it did not work.

    So, the topic of planning just in time deliveries in Spider is closed.

     

    However I have one question regarding SF links

    You write "It means that if you apply SF dependency succeeding activity shall finish AFTER preceding activity start. "

    May be I miss something, but this is not how Spider schedules it, when no resource leveling is used

    In thus case Activity 3 is preceding, activity 4 is succeeding 

    Regards.

     photo SF_links001_01_initial_zps93e6cba4.png

  9. 0
    Vladimir Liberzon ·

    Evgeny,the time difference

    Evgeny,

    the time difference between start and finish in this case is still zero.

    We shall look how to avoid this confusion.

    Regards,

    Vladimir

  10. 0
    Rafael Davila ·

    Vladimir,Of course Contractor

    Vladimir,

    Of course Contractor site security is a hammock (LOE) activity that may finish as soon as owner site security starts. I just did not showed this way for simplicity as in most of my schedules hammocks are frequently defined by a lot of unlinked  activities, I always miss the topic activities but modeling the dragging of a topic activity or MSP Summary Activity is out of Spider functionality.  In any case to show Contractor site security is dragged by the late start of Security by Owner a SF link is needed.

     photo fs02587_zpsd85a3c6d.jpg

    Never say never ... 

    Evgeny,

    Same as you I would schedule just in time using SF links but suppose in MSP an auxiliary milestone under the Summary Task would be needed unless you can create a SF link to the Summary Task.  As Far as I recall links to Summary Tasks are somewhat limited, and this limitation can make sense but I do not have a current MSP license. 

    I do not schedule just in time very frequently but maybe I learned the use of SF links from MSP forum and the security guard issue is just an extension of the concept, somehow it was on my mind.  

    I am glad to know you accept some uncommon link types and are even wanting more such as strict and maximal lag though I have my reserves about full implementation of maximal lag.  It is good that Spider Team listens like no other team, because of you a few good things have already been included. 

    Contrary to what many advocate, that we do not make enough use of milestones I am against their indiscriminate use and use them only when needed. These have been a burden with schedule updates as my clients frequently forget milestone shall be updated and shall match the update of multiple related activities, an update usually different to as planned. They frequently miss some of the multiple links, among them the driving as happened, not necessarily the same as planned  The need for extra milestones to mimic the topic activity is something I hate. 

    Best regards,

    Rafael

  11. 0
    Evgeny Z. ·

    Vladimir,it is clear now. I

    Vladimir,

    it is clear now. I think it was my misunderstanding of what SF relation actually means, which was partially caused by advise of Microsoft to use these types of relations for just in time delivery planning.

    Strangely enough also Microsoft Project does not produce "just in time delivery result", when resource leveling is used.

    I will raise this at Mcrosoft forum.

    Regards.

  12. 0
    Rafael Davila ·

    Add another successor to the

    Add another successor to the just in time delivery activity, most probably ALAP will not do it.

    At times I like to schedule not just in time but close to just in time. Say delivery to be a week or less before installation start. A lag will not do it as it will artificially delay installation if delivery is delayed to 3 days before installation.  

    That our model looks good with early dates is not enough, it shall also correctly model intended float allowances. There are alternative ways to improve the just in time model but unfortunately too intricate.  I hope improved strict links and maximal lag will provide for safer modeling of just in time in addition to many other things. Keeping some limitations on maximal lag shall make it easier to understand the implications. 

    Evgeny,

    If you model just in time in MSP using SF link and no successor to the delivery activity it can be delayed till the end of job, here some convoluted logic must be added for resource leveling and late schedule to work as expected when using SF logic. 

    Still somewhat tricky as you shall take care not to link predecessors to installation activity but to installation start milestone. Needless to say with the use of user defined fields, formulas and filters you can keep it under control. 

     photo convoluted_zpsefcaaef3.jpg

    Best regards,

    Rafael

  13. 0
    Evgeny Z. ·

    Rafael,REAdd another

    Rafael,

    RE

    Add another successor to the just in time delivery activity, most probably ALAP will not do it.

    Not sure what you meant, but it works the way I would want it to.

     photo JustInTimeDelivery_zps99cdda83.png

    RE

    At times I like to schedule not just in time but close to just in time. Say delivery to be a week or less before installation start. A lag will not do it as it will artificially delay installation if delivery is delayed to 3 days before installation.

    What I do normally is the following:

    • I built in some safety buffer at the end of the just in time delivery path.
    • As soon as the the 1st activity of the "just in time delivery path" has started I change the buffer to 0 and change the whole path to have normal ASAP FS logic. See below example
     photo JustInTimeDelivery_updated_zps77272961.png

    Are there any reasons you think it may not work?

  14. 0
    Rafael Davila ·

    Evgeny,The ALAP delivery will

    Evgeny,

    The ALAP delivery will be moved to an earlier time with the added ASAP successor as the new successor will be driving the activity to the left, you just need to follow what I am saying before moving forward to the next issue of modeling some delivery buffer.  It is how ALAP works in Spider, it delays the activity within free float, of course if you apply ALAP to all activities as soon as all activities Free Float is consumed no Total Float will be left. 

    Because what I call the convoluted logic does not depend on how ALAP I believe it should work in MSP as well, sorry I do not have MSP to try it.  It shall also keep the correct logic while resource leveling.  As all the available methods this also have his own traps.

    http://www.mediafire.com/download/521mthbhamyxmb3/RD020.001.sprj

     photo CONVOLUTED03_zps054392ea.jpg

    Phase1 represents a simple model of just in time using a FS link and ALAP for delivery, it look good for early bars as well as for late bars.

    Phase2 represente the above model but with an ASAP successor added to the delivery activity, for early bars it does not model just in time delivery.  This is a trap I was warning you to speed up your understanding of how ALAP works in Spider.

    Phase3 represents the FS method as suggested by others, it looks good for early bars but it misses correct late bars becuase a late delivery will not delay the installation activity. 

    Phase4 represente the FS method that works with the addition of an auxiliary milestone. Early bars and late bars make sense.  But at the expense of adding a milestone that must be correctly updated.  

    Because things usually do not happen as planned the milestone actual date is not as planned, correct update to such milestones is an issue to my clients, either they miss the update or do it wrong.  Frequently these milestones have multiple predecessors and the driving predecessor as planned is not the driving as per as built logic. 

    I believe after Spider improves strict links and implements some maximal lag functionality we will be able to tackle the issue in a safe way, with no traps, that is not so cumbersome, that do not add more milestones that create updating problems. 

    At times less is more but people that make scheduling specifications only see one side and forget how such simple things as adding milestones to "make it clear" complicate things at the time of updating the schedule. 

    Best regards,

    Rafael

  15. 0
    Vladimir Liberzon ·

    Rafael,if JIT is required it

    Rafael,

    if JIT is required it necessary to add SS dependencies from JIT successor and all others.

    In this case phase 2 will be properly schedules.

    It is logical and easier than add and manage unnecessary milestone.

    But still resource constraints may create problems.

    Best Regards,

    Vladimir

  16. 0
    Rafael Davila ·

    Vladimir,Purpose of Phase2

    Vladimir,

    Purpose of Phase2 was to show Evjeny the trap, your workaround of using SS links from successor works without need of any milestone, the idea of the milestone was to avoid the trap and make it work even if you link successor to delivery activity, it also worked, without the trap but with additional milestone.

    I changed all delivery activities to ALAP to fix some issues and added resources, the scenario resource leveling worked as expected. 

    Maybe some maximal lag functionality will provide for it with no such trap, allowing the scheduler to link other activities directly to the JIT activity, this I do not know but will test ProJack Manager to see if and how JIT with some buffer (can be zero) might be modeled. 

    Best regards.

    Rafael

    I have no ProJack Manager license so I cannot save files but can try some simple scenarios. 

  17. 0
    Rafael Davila ·

    Pro Jack got it as expected

    Pro Jack got it as expected with a single maximal link.

    On the following link there is a video, look how the successor to delivery does not drag it to the left, note how at some point delivery float is reduced to zero. Works without need of unreliable workaround and no need to create add milestone. 

    http://www.youtube.com/watch?v=YXTs31c3gUY

     photo pj9901_zps3213b6e4.jpg

     photo pj9902_zps13af1127.jpg

    Best Regards,

    Rafael

  18. 0
    Evgeny Z. ·

    Rafael,I have now had a

    Rafael,

    I have now had a deeper look at you convoluted logic example and, as Vladimir has suggested, it does not work when resource leveling is used. And this was the very reason, why I started discussion.

    See below

    https://docs.google.com/file/d/0B1FBt_G3gCVqSlBuY1RBaGVUVWM/edit

     

     photo RD020002_updated_withresources_zps8cddfa87.png

  19. 0
    Rafael Davila ·

    Evgeny,Can you be specific as

    Evgeny,

    Can you be specific as to where the sequence is wrong and where are the overloads?

    I downloaded your file and checked sequence before and after resource leveling and it looks ok, also run an overloads report and nothing came out after leveling while before leveling there were some overloads. 

    Installation milestone after resource leveling is not driving, but the delivery is, it is the workaround to allow for direct links to delivery activity without it dragging to the left the delivery.

    Best Regards,

    Rafael

  20. 0
    Evgeny Z. ·

    Rafael,I probably did not

    Rafael,

    I probably did not express it correctly.

    The correct statement is: the convoluted logic method works, but when resource leveled, it does not produce the result, which I would consider optimal.

    In my example, the activity Code=401 has been delayed, thus delaying the subsequent schedule, however I would expect, that this activity would be brought forward instated.

    Regards.

    Evgeny

  21. 0
    Rafael Davila ·

    Evgeny,Can you manually level

    Evgeny,

    Can you manually level your sample job without breaking the logic as to yield optimal, optimal that meets all criteria is a delayed job.

    BTW I made some adjustments to the delivery activity as it shall be of the Spider ALAP type and it is possible there is no workaround on MSP, it is possible this was Vladimir warning, not sure.

    You can download the file and test it with any combination of resource loading, one mishap will be enough to prove it does not always yield expected results. Note I added to all phases the link to Installation predecessors, this was also missing.

    As you can see even if it works it is error prone, maximal lag is easier and safer because it is not a workaround, but a direct   mathematical representation of the problem. 

    http://www.mediafire.com/download/dugwg7tj8i7bsyk/RD020.003.sprj

     photo conv01238_zpsa05fb419.jpg

    Vladimir,

    Sometimes for such schedules I wish I could block additional links to specific activities as to prevent errors when using some convoluted logic. Maybe an editable warning for the individual activity will add understanding of why the scheduler issued the lock.  Does it makes sense to you?

    Best Regards,

    Rafael

  22. 0
    Evgeny Z. ·

    Rafael,RE"Can you manually

    Rafael,

    RE

    "Can you manually level your sample job without breaking the logic as to yield optimal, optimal that meets all criteria is a delayed job."

    I would want my schedule to be resource leveled like this

     photo untitled_zpscef9f0fe.png

    instead of like this

     photo RD020002_updated_withresources_zps8cddfa87.png

    Thought I agree with you, that maximum type relation is probably the most correct solution for this problem, because in my case it is possible, that activity 401 can be so much brought forward, that it will not be a "just in time delivery" any longer.

  23. 0
    Vladimir Liberzon ·

    Rafael,I think that the best

    Rafael,

    I think that the best solution is a warning that some constraints (like JIT dependency) cannot be satisfied and why.

    Ignoring any entered data may be more confusing.

  24. 0
    Rafael Davila ·

    Vladimir,What I suggest is

    Vladimir,

    1. What I suggest is some sort of write protect for specific activities to prevent adding llinks to the activity, as selected by the user, a protection the user can toggle on and off, the warning would be displayed if the user tries to add some link to a protected activity. A way to prevent some unwanted changes on some activities because of logic setup, not limited to JIT models it can be for other situations like the convoluted modeling of a topic activity using milestones just that instead of the milestones a few/lot of activities might be locked against adding links. 
    2. Maybe the convoluted reverse logic can also be applied to all or limited maximal lag conditions as it might be it continues to delay predecessors until all maximal are satisfied and if resource leveling do not breaks Spider ALAP. Some adjustment to the location of the auxiliary milestone might be needed for finish maximal links. Could be that the invisible to the scheduler reverse logic milestones and links can prevent the creation of maximal links when they create circular references. 

    Best regards,

    Rafael

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?