Can’t make feature work “Allow Performance Interruptions of no longer then”
In the Open Standard
Evgeny Z.Member for 18 years 9 months
- Created
- 3
- 4
0
Dear all,
I seem not to be able to make the feature “Allow Performance Interruptions of no longer then” to work.
In my test schedule Activity 1 has a calendar with exception on 25 Jan, which with weekend brings interruption of 64 hours., but I just can’t make Spider reschedule activity 1 it to the next week.
The schedule can be downloaded from here (Interrupt.001.sprj)
https://docs.google.com/folder/d/0B1FBt_G3gCVqS1pmZTJqcWI0Qjg/edit
Regards.
Evgeny
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?

