Resource leveling activity interruptions

Rafael DavilaMember for 22 years 7 months
Created
5
4
0

We can specify which activities can be interrupted by resource leveling.

  • What is the best way to report the interruptions on a table report?
  • How to filter for activities with resource leveling interruptions?

interruptions

Activity splitting can be a cause for different values of start and finish float.

5 replies

Oldest first
  1. 0
    Rafael Davila ·

    Before materials leveling the

    Before materials leveling the schedule is not feasible if materials inventories are depleted.

    ML01

    After resource leveling the schedule is feasible.

    ML02
    Bricks Installation B is interrpted by the resource leveling algorithm.

  2. 0
    Rafael Davila ·

    I figured out that with a few

    I figured out that with a few formulas I can create the filter.

    interruptions03

    Still I need a way to report interruption dates.

  3. 0
    Vladimir Liberzon ·

    Hi Rafael,thank you for

    Hi Rafael,

    thank you for noticing that the field Interruptions was missed in the list of project columns.

    Please download the latest version of Spider Project and find column Interruptions in the Other section.

    Filtering by not empty values in this column you will see all activities with interrupted execution.

  4. 0
    Vladimir Liberzon ·

    Start and Finish floats can

    Start and Finish floats can be different not only for interrupted activities.

  5. 0
    Rafael Davila ·

    Start and Finish floats can

    Start and Finish floats can be different not only for interrupted activities.

    • Agree, I just wanted to highlight materials leveling as another reason for start and finish float be different. If during activity execution materials are depleted before activity completion the activity will be stopped until more materials become available.
    • Financial constraints can be another reason for for start and finish float be different.

    financial-constraints-interruptions

    I recall some references(1) about different start and finish float values but I do not recall one that makes reference to activity splitting by consumable/materials or by financial resources leveling engine, perhaps because not all software is capable of such functionalities.

    (1) https://www.scirp.org/html/3-1260010_36837.htm