Skip to content

The way Spider calculates phase duration

Evgeny Z.Member for 18 years 9 months
Created
12
5
0

Dear all,

I just noticd, that the way Spider calculates the duration of a phase is a bit strange for me, or at least this is not what I am used at MSP. 

 photo Project9_1_zpsva4oql63.png  photo Project9_1_MPP_zpspeuttpl8.png

1) Is there a way to show phase duration as the [date of latest activity] - [date of earliest activity]?

2) What is the definition of "Number of working days remaining?"

12 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    By default phase duration is

    By default phase duration is calculated basing on phase calendars and may differ from actual phase duration based on calendars of all activities and resources that belong to this phase. In any case hours and days when no activity of this phase is executed are not counted.

    Spider also calculates total number of work days when the phase activities are excuted. This number is reflected in the field Number of working days. If an activity worked one hour in one day and another hour in the different day then the number of working days will be two. And again periods when no phase activity is executed are not counted.

    Elapsed duration may be easily calculated using formula (manually or automatically), so it does not make sense to create separate field for this data.

    I see that MSP shows elapsed duration and I don't see much sense in phase duration equal to 128 when total duration of all phase activities is 48. We try to apply the same approach to calculating both activity and phase duration counting work time only.

  2. 0
    Rafael Davila ·

    1) Is there a way to show

    • 1) Is there a way to show phase duration as the [date of latest activity] - [date of earliest activity]?

    Just add a Hammoack and you will get the following figure, it should not be difficult to figure it out Phase Duration represents the count of hours [not sum] during which any activity was performed during the phase.

    If you look at Activity 1 Phase after adding the hammock additional hour count happened yielding 88 hours.

    If you have a particular need for phase duration calculation add a user defined field and a formula, easier than creating hammocks, in this case it was just for illustration purposes.

    phase hammock photo phase hammock_zpsg3umgbpf.jpg

  3. 0
    Rafael Davila ·

    Because Phase Calendar is the

    Because Phase Calendar is the union set of all work hours it will be special and can be different to any child activity calendar, so it won't matte what it reads or to what you change it.  Take some time to create a 24-7 calendar assign it to the hammock ans see what happens to the phase duration, then change phase calendars and see what does not happens.

    It works as intended but because of this maybe at phase level no calendar name shall be available.

    PHASE DURATION 02 photo DPHASE02_zpsjx5rwcjz.jpg

  4. 0
    Rafael Davila ·

    One way to visualize summary

    One way to visualize summary bar duration is to think abut Phase Detailed Bar that rolls up all activity bars within the phase.

  5. 0
    Rafael Davila ·

    I hope my few illustrations

    I hope my few illustrations add some visualization to Vladimir's words.

    Best Regards,

    Rafael

  6. 0
    Evgeny Z. ·

    Vladimir, Rafael,thank you

    Vladimir, Rafael,

    thank you for your responses.

     

    RE "Elapsed duration may be easily calculated using formula (manually or automatically), so it does not make sense to create separate field for this data."

    I must be doing something wrong, because I have created a user-defined field (myDuration) to automatically calculate such elapsed duration, but I can't make it work.

    I use formula:

    Diff_Days_Calen ( Fin ; Start ;A  )

    Would anybody be able to have a look at it?

    https://drive.google.com/file/d/0B1FBt_G3gCVqZV9TM0ktWGp1QVU/view?usp=sharingRegards.

    Regards.

    Evgeny

  7. 0
    Vladimir Liberzon ·

    Set My Duration field type to

    Set My Duration field type to Numerical (yours is Date-Time).

    Formula: A=Diff_Days_Calen (Fin ; Start ; "A")

  8. 0
    Vladimir Liberzon ·

    Why cost calculation? It

    Why cost calculation? It should be schedule calculation. Duration is changing when project is rescheduled.

  9. 0
    Evgeny Z. ·

    Vladimir,Ok, thanks. It works

    Vladimir,

    Ok, thanks. It works now.

    I also set the flag for "Execute automatically => In activity Gantt after scheduling". But the strange thing, is that it shows the result of a previous calculation (of a calculation one step behind).

    what I mean:

    step 1; do scheduling 2 times

    step 2: do resource constrained scheduling. Result: the user filed still shows previous value

    step 3: do normal scheduling again. Result: user field now shows the value, which should have been shown in step 2

    step 4:  do normal scheduling again. Result: now it shows correct value

     

    Does it work the way it is supposed t?

  10. 0
    Evgeny Z. ·

    Vladimir,thare was a typo in

    Vladimir,

    thare was a typo in my original post. It is " In activity Gantt after scheduling". But the problem, that user filed displays results of the previous step calculation is still there

    https://drive.google.com/file/d/0B1FBt_G3gCVqTUxVd2NlYjNmLWs/view?usp=sharing 

  11. 0
    Vladimir Liberzon ·

    Evgeny, I downloaded your

    Evgeny, I downloaded your project but can not repeat your results.

    In my notebook everything works as expected. Very strange. Did you try Demo with this project?

  12. 0
    Evgeny Z. ·

    Vladimir,I upgraded to the

    Vladimir,

    I upgraded to the latest version (11.03.103) and it works fine now

    Regards.

    Evgeny

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?