Skip to content

Introduction of unachievable NLT constraint slightly extends the schedule

Evgeny Z.Member for 18 years 9 months
Created
0
4
0

Vladimir,

I am still experimenting with prioritization and I noticed, that when I introduce my favorite NLT constraint into the j3013_8  RCSP then, when resource leveled, Spider actually produces a longer schedule, than without resource NLT constraint. The extension is not big, only 118 days vs 114, but still, since this is the only prioritization I use and I set it to the finish milestone, then I did not expect this to happen, since I thought that all preceding activities would have the same NLT constraint-driven priority.

I must say, that in the past I did not notice such effect of NLT constraint, but I was experimenting only with simple schedules.

Is there an explanation for this?

https://drive.google.com/file/d/0B1FBt_G3gCVqNUE0SEE1Q2VybjA/view?usp=sharing

Regards.

Evgeny. 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?