Gantt online from Spider Project

Ivan VasilMember for 7 years 4 months
Created
7
41
0

Hello everyone, did the script upload from Spider Project (version and revision does not matter) to the site (your internal portal or public site) here is a link to the youtube channel

https://www.youtube.com/watch?v=X722tu2P1Tc (video without sound, with subtitles)

from the possibilities so far only a drilateral upload from the program. In short, there is a template configured once, a report is generated on it, this report is saved in a text file with any name, then the script is run with the file name, the output is a file with the format for the site, copy to the site and get the visualization. But this sequence can upractice say to create a script in spider project and in the script to specify which folder what is the name of the file to take and where to copy ie in fact can automatisiert to a single action either, but it ... often the program itself will formiruet updated information on the website. Hope explained clearly)

7 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Hi Ivan,explanation is not

    Hi Ivan,

    explanation is not clear but your video shows what and how can be done.

    Today Spider Project users can place project and portfolio Gantt Charts to the Web but this feature is not available for the users of older versions.

    In any case your idea is right and using the same approach it is possible to show not only Activity Gantt Charts but also Resource Gantt Charts and other reports to project stakeholders.

    If you want to do the same but for people with limited access rights you shall open the project with required rights and then export to text required data. Everything that shall be hidden will not appear in the text file.

  2. 0
    Marcus Possi ·

    Hi Ivan, Yes. There are some

    Hi Ivan,

     

    Yes. There are some and very useful News in Spider Project since last month.  With just a simple menu item spider project manager will be able to export he “Gantt Chart” and selected items to web, and then, make the most important data – under logins and passwords, available to stakeholders that you have to report.

     

    “Today Spider Project users can place project and portfolio Gantt Charts to the Web but this feature is not available for the users of older versions. Everything that shall be hidden will not appear in the text file.” – by Vladimir.

     

    You may have a glimpse at https://www.youtube.com/watch?v=VHA7ntc3ses

     

    And its performance (web publishing) in its first interface – still under development. https://www.youtube.com/watch?v=5gzj3vkLUvg

  3. 0
    Paulo Junior ·

    Hello. Ivan,Spider in my

    Hello.
     
    Ivan,
    Spider in my opinion is the best project management tool, it's already the specific tool for engineering project management.
     
    The only one capable of meeting all Pmbok needs without API or Plugin assistance, the most robust and fast option when managing complex scopes, now able to inform and receive status for 21st century teams, companies with teams in multiple locations now You have the option to control and track everything remotely.
    Another differential that only the best can offer.
     
     
    And its performance (web publishing) on its first interface - still under development. https://www.youtube.com/watch?v=5gzj3vkLUvg
     
    Doubts and training information:
     
     
     
    Paulo Cabral Junior, 
     
    Spider Project Professional Specialist,
     
    Consulting and training.
  4. 0
    Ivan Vasil ·

    Soon I will finish also

    Soon I will finish also formation of schedules of the reporting on the project, need of people, percent of performance, financial information, labor input the plan the fact and so on, all this with unloading on the website

  5. 0
    Vladimir Liberzon ·

    Very well Ivan,Let us know on

    Very well Ivan,

    Let us know on your achievements and if you need any improvements for your tasks..

    Best Regards,

    Vladimir

  6. 0
    Marcus Possi ·

    Hi Ivan, The former Spider

    Hi Ivan,

     

    The former Spider Project WEB ...

    “Today Spider Project users can place project and portfolio Gantt Charts to the Web but this feature is not available for the users of older versions. Everything that shall be hidden will not appear in the text file.” – by Vladimir.

     

    You may have a glimpse at the conceptual idea at https://www.youtube.com/watch?v=VHA7ntc3ses

     

     

    Now became greater Spider Project WEB-PI

    “Today Spider Project users can input performance data by any Browser under the proper security system. Spider Team finished their last efforts" – by Marcus Possi.

     

    You also may watch it running at https://www.youtube.com/watch?v=tj44gKEntaM&feature=youtu.be

  7. 0
    Alexandre Faulx-Briole ·

    Hello Vasil,your video demo

    Hello Vasil,

    your video demo certainly is interesting; as I do not read Russian, could you please post a new demo in English?

    thank you,

    Alexandre

Log in or join to reply