Filter activities by resources

Evgeny Z.Member for 18 years 9 months
Created
38
6
0

Dear all,

is there a way to filter activities, which have certain resources assigned? E.g. I want only activities, which have resource A and B assigned

 

38 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    This is easy.In the activity

    This is easy.

    In the activity Gantt Chart menu select Filter/Only activities that use ... /Resources and then choose resources in the list.

  2. 0
    Bogdan Leonte ·

    Hello,here is the full

    Hello,

    here is the full answer.

    https://ibb.co/3czryJC

    Also you can select any column and filter any resources that meets certain criteria.

  3. 0
    Vladimir Liberzon ·

    This is another way:

    This is another way:

    Filter
  4. 0
    Evgeny Z. ·

    Vladimir, Bogdan, thanks! It

    Vladimir, Bogdan,

     

    thanks! It works!

     

    Just to check my understanding

    1) There are built in filters, which one can access through Filter menu (e.g. activities without preicessors only etc)

    2) it is also possible to build own filters by clicking filter icon

     

    Questions:

    Q1) Can I build manually filter with equivalent functionality to the one of built in filter (e.g. activities without preicessors only)?

    Q2) When I build a new filter manually, can I re-use (refer to) built in filter? E.g.: activities without preicessors only AND something else

    Q3) When filter is applyed, can I see exactly which filter is applyed and which logic?

  5. 0
    Bogdan Leonte ·

    Evgeny,Q1) Can I build

    Evgeny,

    Q1) Can I build manually filter with equivalent functionality to the one of built in filter (e.g. activities without preicessors only)?

    Yes.

    Q2) When I build a new filter manually, can I re-use (refer to) built in filter? E.g.: activities without preicessors only AND something else

    No you cannot refer tu built in filter, but you can build any number of simple filters and then combine them into one complex filter. This complex filter can contain simple filters and formulas also.

    Q3) When filter is applyed, can I see exactly which filter is applyed and which logic?

    In the lower part of the window you may see which filter is applied, number of rows selected, filter on links.

    If you see which filters are applyed then you know the logic.

    Also you can undo filters from the Action->Undo table and you can undo them in random order. (An action once undone, it cannot be redone)

    Hope this aswers your questions.

    Best regards,
    Bogdan

  6. 0
    Evgeny Z. ·

    Bogdan,thanks! I just now

    Bogdan,

    thanks! I just now need to understand how to use all this magic

  7. 0
    Bogdan Leonte ·

    This is not a filter, it is

    This is not a filter, it is more of a report, but it has some advantages in the sense that it also displays amount of resource hours, volumes of work, costs and so on and so forth.

    What I am talking about is Project Truncation, you can find it the Reports and Diagrams->Project truncation.

    It creates a truncation of the project between 2 dates or from data date +/- number of days.

  8. 0
    Rafael Davila ·

    Evgeny,For how to use this

    Evgeny,

    For how to use this magic please follow the steps.

    1 Filters-01 2 Filters_02

    3 Filter-03-Create-Filter 4 Filter-04-Before-applying-filter Before Filter

    5 Filter-05-after-filter-for-duration-greatern-than-3-days  After Filter Apply-filter

    After creating a few simple filters try something more complex and come back with your questions.  Perhaps lookahead filters.

    6 Filters-06 7 Filters-07

    You can download the following file to explore a few look-ahead and look-back filters.

    http://www.mediafire.com/file/sidwwv9lorbs0cc/Filters-A.002.sprj/file

    As they do not depend on UDF you can copy and paste them into other files without any UDF code conflicts.  Or you can transfer the following Reference Book.

    http://www.mediafire.com/file/zqpb4vqwbjm2464/Filters_Lookahead.001.sdoc/file

  9. 0
    Bogdan Leonte ·

    Evgeny,you may also want to

    Evgeny,

    you may also want to look into layouts because if you apply filters and then save the layout into the project then it will remember the filters.

    For example you may want to create a 2 weeks lookahead + filter all activities that use resource B. You can either create a simple filter for these 2 conditions or 2 filters and 1 complex filter with the 2 conditions.

    After this you can save the layout as 2 weeks lookahead and when you call it it will automatically apply the filters. Layouts can also store columns (order, size), level of detail of the WBS, report diagrams, scale of the gantt chart, pretty much anything.

  10. 0
    Rafael Davila ·

    Evgeny,For activitiew without

    Evgeny,

    For activitiew without predecessors the filter is.

    NOPRED-FILTER-01

    to mean field is empty use two quotation marks (") + (") with nothing in between, that is ""

    NOPRED-FILTER-02
     

  11. 0
    Rafael Davila ·

    Bodgan,What is the difference

    Bodgan,

    What is the difference between what you call simple and complex filters? 

    • Perhaps you mean when using AND/OR/NOT conditions?
    • Perhaps when inserting other filters?
    • If not enough inserting functions, field[modifier] or formulas can also complicate the filter.

    Best Regards,

    Rafael

  12. 0
    Bogdan Leonte ·

    Rafael, maybe complex isn't

    Rafael, maybe complex isn't the right word, compound is a better one. When I say complex filter I mean that Filter (C) is made from Filter (A) AND/OR/NOT Filter (B).
  13. 0
    Rafael Davila ·

    Bodgan,I wonder if there

    Bodgan,

    I wonder if there might be more complexity, maybe they are relational if written in this way instead of copy-paste the isntructions as text.

    If a change is made on referenced filter it will notice?

    What if circular references among filters are created?

    It looks like they are relational.

    Circular-Dependency-on-filters

    I did not know, thank you once again.

    Now I know I have the option to copy-paste instructions to keep them separate or use insert filter to keep them related.  A drawback is that you unknowingly can delete a related filter.  Always keep a reference book in case you need to restore some deleted filters.

    Best Regards,

    Rafael

  14. 0
    Bogdan Leonte ·

    Rafael,I don't think the name

    Rafael,

    I don't think the name matters, the ideea is that you can created create filters by referencing other filters.

    What I haven't been able to figure out so far is how to use formulas inside filters; I don't even know how it would be useful, but I suppose Vladimir will be able to give us a comperhensive answer.

    Best Regards,
    Bogdan

  15. 0
    Vladimir Liberzon ·

    Bogdan, very simple example

    Bogdan, very simple example for filter defined by formula: show activities where expenses are larger than contract cost.

  16. 0
    Evgeny Z. ·

    Rafael,your

    Rafael,

    your function f_PredOpers="" works very fine!

     

    Question: where is it all documented? There is nothing I could find in  Spider help regarding f_PredOpers 

  17. 0
    Vladimir Liberzon ·

    Evgeny,f_PredOpers - field

    Evgeny,

    f_PredOpers - field (column) code.

    Spider Project shows activity predecessors and successors in the Gantt Chart columns.

  18. 0
    Rafael Davila ·

    I have no Spider

    I have no Spider Documentation other than Spider Help, I learned it by experimenting with sample files as well as through Planning Planet where Vladimir is always available in short time.  Once you learn the basics you will see there is no need to memorize the field names, no need to memorize formulas.  While spider has a script language I know no single command, I just record the script by typing as if recording an Excel Macro.

    To get the fields while creating a filter:
    Click Filter from Menu
    Click Apply
    Click New 
    Click Field
    Select field – there you will see the field names and codes

    Select-Fields

    I use Planning Planet to learn, at times by asking questions, at times by answering questions.  Today was good day, I learned a few things about Spider Filters I did not know.

  19. 0
    Evgeny Z. ·

    Rafael,thanks! Vladimir, is

    Rafael,

    thanks! 

    Vladimir, is this a part of the standard Spider training?

  20. 0
    Evgeny Z. ·

    RE<<you may also want to

     

    RE

    <<you may also want to look into layouts because if you apply filters and then save the layout into the project then it will remember the filters>>

    Ok, at looked at layouts. But I think I am missing feature Layout => Load from project (activate saved layout)

    I have: 

    Layout => Load from file

    Layout => Save to file

     

    Layout => Save in project

    But not Layout => load from project ??

  21. 0
    Rafael Davila ·

    Be reminded that it is

    Be reminded that it is possible for activities to have both predecessors and successors yet still suffer from dangling – hence inadequate – schedule logic.  These cases – generally categorized as dangling finish and dangling start – are also known as “orphan relationships.”

    In Spider Project:

    • Filter for Activities without Successor from Finish only will filter out dangling finish activities.
    • Filter for Activities witout Predecessor to Start only will filter out dangling start activities.


    Filters-for-Dangling-Logic

    You can make use of "Preceding activities to start" and "Succeeding activities from finish" fields to create the filters by your own.  Spider Project is very powerful software; it might have many fields you do not even imagine.
     

  22. 0
    Bogdan Leonte ·

    You cannot load from

    You cannot load from project.

    Spider uses reference-books in order to transfer data from one project to another.

    Here is are 2 sample movies:

    1. How saved layouts work:

    https://youtu.be/CnLRBLKag3Q

    2. How to create and transfere layouts reference-books:

    https://youtu.be/5mAhwhLCjUw

    In conclusion, you have to create the layout which contans filters, WBS structure, WBS Level, Diagrams, columns, Gantt scale, etc.; save it in the project or in a file.

    If you save it in a project you have to create a reference-book of the Layouts table in order to transfer it into another project.

    If you save it into a file then you can loaded into any project without reference books.

    Also form the main Spider windows you can set in the Options of new projects and documents a default Layout file which will be applied to any new project created.

    Hope this clarifies some things.

    Best regards,
    Bogdan

  23. 0
    Bogdan Leonte ·

    Vladimir,in your example the

    Vladimir,

    in your example the filter would be s_pln_ContractPrice <  s_pln_ContractCost

    However you have a button in the filter creation window you can enter in the filter Fomulas that were previously created; how do you use them?

    https://ibb.co/cLhZ07v

  24. 0
    Rafael Davila ·

    First project instructions is

    First project instructions is a good way to start learning Spider.

    Reference-Books-01

    Reference Books are introduced under First project instructions.

    Reference-Books-02

    You transfer the Reference Books by opening the desired target schedule(s) as well as the Reference Book where you click menu Document then Data Transfer and make your choices.

    Reference-Books-Data-Transfer

    You can try with the following Reference Book.

    http://www.mediafire.com/file/zqpb4vqwbjm2464/Filters_Lookahead.001.sdoc/file

    Unfortunately Filters and Formulas are not introduced here.

  25. 0
    Evgeny Z. ·

    Bogdan,thanks! It helps a

    Bogdan,

    thanks! It helps a lot!

    souch video instructions - is something I a missing in Spider!

  26. 0
    Rafael Davila ·

    You can also try Spider

    You can also try Spider Project Help for information on Reference Books.

    Spider-Project-User-Guide-01     Spider-Project-User-Guide-02

    Reference Books are one type of document used by Spider Project stored as separate files, search on Spider Help for “Documents”.

    Think of a Reference Book as a table you can transfer to a project file that contains many tables.
     
    If one Reference Book, say a Filters/Formula Reference Book, contains user fields you must also transfer the corresponding user fields via another Reference Book for it to work as expected. Before transferring the UDFs, make sure there are no duplicated UDF codes if you need them to be different. You might edit the UDF codes within the Reference Book to avoid conflict, when transferring non existing codes will be created.

    Any correction and clarification by Vladimir will be welcomed.

  27. 0
    Rafael Davila ·

    It might be that Planning

    It might be that Planning Planet be a good place to provide additional guidance in the form of links to white papers and videos. Could be a win-win for Planning Planet, Spider Development Team as well for Spider Users.

    http://www.planningplanet.com/advertisers/spider-project-team

  28. 0
    Vladimir Liberzon ·

    Bogdan,previously created

    Bogdan,

    previously created formulas may be used for filtering repeatedly if necessary.

  29. 0
    Bogdan Leonte ·

    In Spider there is an option

    In Spider there is an option Activities with filtered links only - after filtering links when you apply this filter spider will show only activities which have visible links in the links table

    Maybe Vladimir would consider creating a built-in filter similar to the one above but for resource assignments - you will filter resource assignments and then apply the filter Activities with filtered assignments only

    And maybe another one named Filtered assignments only - which will show activities and assignments, but only the visible assignments.

    What do you think?

  30. 0
    Rafael Davila ·

    I believe Spider Project

    I believe Spider Project Filters should be able to filter what I have done with Excel as I consider resource filters to be a matter of the utmost importance. Using Spider Interface, perhaps if using some kind of modifier to deal with indentation.

    Complex-Filter

  31. 0
    Bogdan Leonte ·

    Rafael,In Spider it is

    Rafael,

    In Spider it is possible. There is a Column (in the Other) group called Assigned Resources. This columns shows assigned resources similar to MS Project, see picture:

    https://postimg.cc/gxhbB84Z

    Then you can create filters to show activities containing only desired resources (no matter how many); however when expanding to assignments, all asignments will be visible since the filter is applied to the activities.

    Here are some sample filters using this column:

    • Contains ( f_Resources ; 'A' ) and Contains ( f_Resources ; 'B' )
    • Contains ( f_Resources ; 'A' )
    • Contains ( f_Resources ; 'B' )
    • NOT Contains ( f_Resources ; 'A' )

    PS I used A, B, C from Resource A, Resource B, Resource C. Using the Contains ( ; ) function you will have to specify the name of the resource as it appers in the resource table.

    I think this is a reasonable solution.

    Best regards,
    Bogdan

  32. 0
    Rafael Davila ·

    RESOURCE FILTERS ARE EXECUTED

    RESOURCE FILTERS ARE EXECUTED ON RESOURCE ASSIGNMENTS VIEW
    We might want to filter for:
    1) Activities with certain resource: Say activities with Resource A
    2) Activities with either one resource: Say activities with either Resource A or Resource B
    3) Activities with all selected resources: Say activities that include Resource A and Resource B; I do not know hot to create such filter within Spider Project but can be done outside of Spider Project if using Excel.

    Resource_Filters_01 Resource_Filters_01B Resource-Filters-02 Resource-Filters-03  Filter-Resource-A-B RESOURCE A&B FILTER YIELDS NONE

    Resource-Filters-04  Resource-Filters-05 Resource_Filters_06

    Click this line to download the Excel worksheet

    Frequently I am interested in looking for activities that have certain resource but is missing another. If missing the companion resource then it shall be fixed.

    FILTER-RESOURCE-A-BUT-NOT-C

    Do you know a better way to filter for Activities that include Resource A and Resource B? and what about Activities that include Resource A but not Resource C?

  33. 0
    Rafael Davila ·

    Bogdan YOU MADE MY DAY, the

    Bogdan YOU MADE MY DAY, the filters work directly from Gantt.

    Thank you. hats-off-salute-smiley-emoticon

    Resource-Filter-on-Gantt

    Resource-Filter-on-Gantt-A-or-C

    Filter-contains-Resource-A-but-not-C    Frequently I am interested in looking for activities that have certain resource but is missing a required companion resource. If missing the companion resource then it shall be fixed.
     

  34. 0
    Vladimir Liberzon ·

    Rafael,it can be done but in

    Rafael,

    it can be done but in three steps.

    First filter for activities that use resource C, then invert this filter, then filter for activities that use resource A keeping previous filter.

  35. 0
    Marcus Possi ·

    Hi. I do think that you may

    Hi. I do think that you may find something helpfull in http://www.spiderproject.com/index.php/books in English. The majority of our work is written in Portuguese, but there is something about in our fourth edition. there is another one in English, about Spider Project WEB, but it is not the focus here. BR,
  36. 0
    Rafael Davila ·

    Vladimir,Thanks, I copied

    Vladimir,

    Thanks, I copied your note into my reference file under specific filter notes box for future reference.

    Bogdan,

    Thanks, once again. I copied your note regarding the field for Assigned Resources into my reference file under project properties notes box for future reference.

    Marcus,

    Thanks for the reference.

    Best Regards,

    Rafael

  37. 0
    Vladimir Liberzon ·

    Rafael,to be sure that

    Rafael,

    to be sure that companion resources are not missed create and assign multi-resources.

  38. 0
    Rafael Davila ·

    Agree, better use

    Agree, better use multi-resources whenever possible.

    The advantage of multi-resources is that by modifying them you can apply the modification to all or specific multi-resource assignments.  Companion resources can be as many as needed which can complicate verification.

    Multi-resources are great, but not always you use them (for whatever reason) so filters are still handy.

Log in or join to reply