Intro to and Learning Synchro

S MMember for 14 years
Created
1
11
0

Having been a Planner for 12 years on P6, MSP and Pertmaster I feel that the future of Planning is the move towards 4D Planning and its incorporation into Gantt and Site Planning.

 

Having no prior experience of 4D Planning as within the UK from trying to attend Training courses and organisations that have adopted the practice it still seems in its infancy. What would be the best way to upskill in 4D Planning / BIM and do you feel that Synchro would be the best software to train in?

 

Any other tips on entering the 4D Planning world would be greatly appreciated :)

 

Thanks,

1 reply

Oldest first
  1. 0
    Vladimir Liberzon ·

    3D model can be used as an

    3D model can be used as an initial information for planning and scheduling.

    The results of project planning and scheduling can be presented as 4D and 5D reports together with Gantt Charts, Time-Location Charts, etc.

    The scheduling itself does not depend on the ways of getting initial data and presenting project schedule and budget.

Log in or join to reply