I have a pipeline project that has reversed direction - see my previous post. I’ve been able to resolve the issue of reversing the start & end chainages and dates for each activity using Excel, and I can add reversed links to Tilos using Excel. However, I have not found a way to delete existing F-S links in Tilos using Excel so they can be replaced by necessary new F-S links. If I do add my new F-S links to the reversed activities circular links are created:(
Any clues on how to delete links using Excel?
Cheers
TRB
Any clues on how to delete links using Excel?
Cheers
TRB