Baseline from another File or Excel

Vasat ToreMember for 19 years 6 months
Created
3
5
0

Hi everyone,

 

I have 2 TILOS files and I want to set one of them as baseline to the other.

What is the best way to do this?

 

Thanks

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Vasat,I hoped that

    Hi Vasat,

    I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject

    When you baseline a project, my experience is that you can only select activities in the current project.

    Did you ask the question to Tilos people?

    All the best,

    Alexandre

  2. 0
    Vasat Tore ·

    Hi Alexandre, Thank you for

    Hi Alexandre,

     

    Thank you for your response.

    As I came to find out, there doesn't seem to be a way to do it the way I described.

    My work around was to save the baseline in TILOS and progress the activities based on the other.

     

    Cheers,

  3. 0
    Santosh Bhat ·

    Vasat, Chuck the data into

    Vasat, Chuck the data into Turbo-Chart (https://turbo-chart.com) and it'll allow you to see two scehdule datasets on one chart.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?