Number of Layers - restriction

Luca BasileMember for 23 years 3 months
Created
5
5
0

Hi

Been new of TILOS i created my first time-chainage schedule, but I found that the 7 allowed layers in TILOS are a considerable restriction

I tried to add more layers, but I was not able.

Could anyone help me, clarifing if TILOS allows more than 7 layers, and in the case how to create them?

 

 

Cheers

Luca

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Luca What operating level

    Hi Luca

    What operating level are you set to?

    Go to Help > User Level and select Advanced - then you can add as many layers as you wish.

    Best regards

    Mike Testro

  2. 0
    Luca Basile ·

    Hi Mikethanks for the reply I

    Hi Mike

    thanks for the reply

     

    I have the Advanced Mode activated, but still I am do not have the Add Icon enable or visible in order to add more layers

    I open the "Layer" tab with the time-chainage grid selected. Is there any other place where i do need to go?

     

    Thanks
    Luca

     

    PS
    I am using Tilos &.1.01

  3. 0
    Mike Testro ·

    Hi Lucas The answer is in

    Hi Lucas

    The answer is in Library Explorer

    Goto Help > Search > Type "Layers" > List Topics and the route is explained under Defining Layers.

    BTW PowerProject v 12 now has a time chain conversion option from its Task Per Line mode.

    Best regards

    Mike Testro

  4. 0
    Luca Basile ·

    Hi Mikethanks, it did

    Hi Mike

    thanks, it did work

     

     

    Luca

  5. 0
    Kai Pyn Tan ·

    Hi,very useful tips,

    Hi,

    very useful tips, thanks.

    Besides, can TILOS assign 2 layers to a activity? if yes can anyone guide me how to do it?

     

    Regards,

    Kai Pyn

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?