Hello PPers,

Is it possible to assign two different layers to the current task and its baseline?

Thank you

1 reply

Oldest first
  1. 0
    Thorsten Balthasar ·

    Alexandre,No, task and

    Alexandre,

    No, task and baseline has the same layer, but:
    if you want to switch off the visibility of selected baseline tasks you may use the "Visible" flag in the baseline manager.

    regards

    Thorsten