Summary task disappears

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
2
2
0

Hello Planners,

One customer of mine is having hard time with his Tilos project: one of the project summary tasks is no longer visible and clickable in the Time Distance View, although it displays normally in the Gantt Chart and the subproject Tasks List

Can anybody help?

Thanks a lot

Alexandre

2 replies

Oldest first
  1. 0
    Thorsten Balthasar ·

    Dear Alexandre,for a

    Dear Alexandre,

    for a Time-Distance Cell it is possible to switch off the display of the Summary Tasks. Please check in the Tab "Expand State" of the Time-Distance-Cell, if the display of the Summary tasks is switched off.

     

    regards

    Thorsten

  2. 0
    Alexandre Faulx-Briole ·

    Thorsten,thank you for your

    Thorsten,

    thank you for your help; where is the "Expand Sate" tab (or field?) that you have mentionned, I cannot find it either in Tilos 8 in English or anything to be compared in Tilos 7 French

    (10 mn later) : I have found the Expand State option in the Summary Task tab of the Time Distance cell properties; thanks again for your help

    Alexandre