100% of the cost at the beginning of the task

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
1
3
0

Hello,

I need to allocate a lump sum cost to some tasks of the project, and have 100 percent of the cost showing at the very beginning of the task. Can anybody help?

Alexandre

1 reply

Oldest first
  1. 0
    Thorsten Balthasar ·

    Alexandre, by default TILOS

    Alexandre,

     

    by default TILOS spreads the cost allocation on the duration of the task.

    For your need you may
    - create a milestone for each of the corresponding tasks
    - assign Start-Start-Links to locate the Milesones at the beginning of the task

    - assign the cost to the milestone
    - you may also switch off the display of those milestones with layers or filter

     

    regards

    Thorsten