Link lines in Time Distance View

Vignesh SMember for 11 years 5 months
Created
2
4
0

In the project which I am working on, most of the activities have more than one predecessor/successor links(usually 5+). Also, no. of activities is 1000+. If I link all of them, the time-distance view looks much clumsy and there is no clarity of schedule presentation. But, none of the links are avoidable as it will affect the dpendency logic behind the schedule and future updation of the schedule will also be a cumbersome one. Is there any option available to make some of the link lines invisible.???

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Vignesh,Try by

    Hello Vignesh,

    Try by selecting different layers for the links you want to display and the others; select the link and open the properties box, you will find the "Layer" field

    Alexandre

  2. 0
    Vignesh S ·

    Alexandre,Thanks for the nice

    Alexandre,

    Thanks for the nice suggestion and this works well as per my requirement.

    Vignesh