Skip to content
schedule1 min read

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.For example:We have a team which can cast 10 m3 of concrete per day (This is Productivity)We have an Foundation which take 100 m3 concrete.Duration of Foundation activity will be 100 / 10 = 10 daysNow we will do it in

Khuong DoMember for 16 years 7 months

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture:

How to define Productivity in Primavera P6 and create schedule-1

First we need to change Duration type of all activity to "Fixed Units/Time"

How to define Productivity in Primavera P6 and create schedule-2

Go to menu Enterprise -> Resources.

Create new Resource like below picture:

How to define Productivity in Primavera P6 and create schedule-3

We will define Productivity for Concrete resource.

Select Concrete resource. Go to Detail tab -> Default Units/Time. Enter value: 10

How to define Productivity in Primavera P6 and create schedule-4

Go to menu Project -> Activities.

Assign Concrete resource to activities.

How to define Productivity in Primavera P6 and create schedule-5

How to define Productivity in Primavera P6 and create schedule-6

We will change the Budget Units to 100 (This foundation need 100 m3)

How to define Productivity in Primavera P6 and create schedule-7

We can see activity duration will change to 10 days.

How to define Productivity in Primavera P6 and create schedule-8

We will do in similar way for other activities.

Now you know how to define Productivity and create schedule from it.

BONUS:

If you have more than one resource assigned to activity, the finish date of activity will be the latest finish date of all resource.

I will add 1 more resource : Backfill

And adjust the Budget Unit to 1000

How to define Productivity in Primavera P6 and create schedule-9

The Finish date of Backfill is 20-Dec-16, later than finish date of Concrete (10-Dec-16). So the activity will finish on 20-Dec-16

How to define Productivity in Primavera P6 and create schedule-10

And one more thing.

The Start date of Backfill can not be same as Start date of Concrete. So we will add a Lag value for Backfill.

Enter 12 days in Original Lag column.

Backfill will start on 13-Dec-16.

How to define Productivity in Primavera P6 and create schedule-11

Now we have a more realistic schedule.

About the Author : Khuong Do

Khuong Do is a Project Planner / Scheduler in Civil Engineering, Transportation, and Oil & Gas Industry. He has worked as a Primavera Consultant Specialist since 2006 and willing to share his passion for Primavera through lots of Tips & Trick on his personal blog : https://doduykhuong.com

Last updated 30 Oct 2025.

2 comments

Oldest first
  1. Rafael Davila ·

    If higher productivity resource is not available then a resource with lower productivity can perform the work and the activity will take longer.

    How do you perform basic resource leveling considering different resources might be avilable each having different productivities?

  2. Rafael Davila ·
    • Backfill and concrete are activities, not resources. 
    • They each take differente resources that must be leveled.

Log in or join to comment