How to define Resource Productivity in Primavera P6 and create schedule
When create a schedule, we can based on Resource Productivity to estimate duration.For example:We have a team which can cast 10 m3 of concrete per day (This is Productivity)We have an Foundation which take 100 m3 concrete.Duration of Foundation activity will be 100 / 10 = 10 daysNow we will do it in
24 Nov 2017 · Khuong Do · 1 min read