+ or - adjustment to the overall project duration
In the Open Standard
Stewart GreenMember for 20 years 2 months
- Created
- 3
- 3
0
Because Powerproject doesn’t have the same "global edit" facilities of P3, I’ve used the mass-edit capabilities of Excel to extend or reduce the overall duration of a previously prepared programme.
Good with any number of activities (and ALL activities share EQUALLY in contributing to the longer or shorter overall duration).
Epecially useful in "massaging" programmes that contain a high number of activities.
Useful eg:
to create a (shorter) Target Programme from a previously prepared detailed Contract programme.
to create a (longer) Contract programme from a previously prepared detailed Construction programme.
Also useful for preparing "what if" examples of different overall durations
If interested, please just email, and I’ll send over a method sheet
Cheers
Stewart
Good with any number of activities (and ALL activities share EQUALLY in contributing to the longer or shorter overall duration).
Epecially useful in "massaging" programmes that contain a high number of activities.
Useful eg:
to create a (shorter) Target Programme from a previously prepared detailed Contract programme.
to create a (longer) Contract programme from a previously prepared detailed Construction programme.
Also useful for preparing "what if" examples of different overall durations
If interested, please just email, and I’ll send over a method sheet
Cheers
Stewart
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?