Formula to display the duration including holidays
In the Open Standard
Andrew OwensonMember for 18 years 4 months
- Created
- 3
- 3
0
My duration column will display the duration of the task excluding holidays. What I need is to display the duration including any holidays in the programme. so if it ran over a bank holiday, the duration would be 5 +1, if that makes sense. In excel I would use Networkdays & not add the holidays.
Regards Andrew
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?

