Laurie WillisMember for 20 years
Created
3
1
0
Hi,

If you have multiple calendars, how can you check which calendar you have previously assigned to a task without adjusting the task length.

Thanks, Laurie

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Laurie,
    Right click on the task bar to open the Properties dialog, select the Task tab, read the Calendar field; use this field to possibly select another calendar.
    All the best,
    Alexandre
  2. 0
    Laurie Willis ·
    Got it. Thanks Alexandre.
  3. 0
    Jamie Robson ·
    Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
    Good luck!
    Jamie