Problems assigning specific calendar to only a few tasks?
In the Open Standard
Mark McErleanMember for 14 years 5 months
- Created
- 4
- 4
0
Hello!
I am trying to assign a 7 day week calendar to 2 tasks on my project. The remaining 100 or so are the standard 5-day 8 hour calendar.
However when I drag the '7 day week, Bank Hols & Xmas' to the tasks and release it all of the other tasks change to a 7 day calendar! I have noticed a few dont however.
90% of the tasks are linked so it it related to that?
Thanks