Automatically assign codes

Konstantinos ParsalidisMember for 20 years 7 months
Created
2
2
0
I am trying to find out whether there is a way to set up an automated assignment of codes once it is partly or 100% progressed, i.e. once I input the progress of the task, the code will automatically change to (e.g.) "Partly Completed" or "Completed" (which I have set up!). I am using PowerProject V9.

Thanks!

2 replies

Oldest first
  1. 0
    Tom Howard ·
    Use the progress token called "Process State"... titles cant be changed but represent similar headings to those you require.
  2. 0
    Andreas Ronczka ·
    You could also use a column with the token "priority" in the spreadsheet and set in the field "indirection" the formula "Percent complete#0#99".
    As result you get a colum where 0% shows RED, 1-99% shows ORANGE and 100% shows GREEN. Not a code but looks simelar.

    HTH

    Andi