How take make a task which fills the gap between another two task, and is automatically adjustable

Ben JokosenumiMember for 10 years 2 months
Created
5
5
0

Hi,

I have the following question, on which I couldn’t find and answer in google.

How to make a task with flexible duration, which will fill the gap between other 2 tasks and will automatically adjust it’s length:
Example 

Task1: Deliver building material (fix start task)
Task2: Guard delivered building material (fixed units)
Task3: Build building (fix start)

So, I want Task2 to fill the gap between task 1 and task 3. I want it to adjust it’s length depending on how late task 1 finishes. So, that it will always start when task 1 is finished, and will always finish, when task 3 starts. Is it possible with Asta?
thanks

5 replies

Oldest first
  1. 0
    Robert Bell ·

    Hi Ben,I would have thought

    Hi Ben,

    I would have thought Asta has "Level of Effort" type tasks......?

  2. 0
    Mike Testro ·

    Hi BenUse a BUFFER task.Creat

    Hi Ben

    Use a BUFFER task.

    Creat a normal task using FS links and then Make Into> Buffer.

    This is unique to Asta and does precisely what you wish.

    There is an option to make it critical or not.

    Best regards

    Mike Testro

  3. 0
    Ben Jokosenumi ·

    Hi Mike, Making it into a

    Hi Mike,

     

    Making it into a buffer task will only affect the start of the buffer task depending on the movement of its predeccesor, the back end of the buffer task will have a deadline constraint applied to it. What if i want the completion of a seperate task to drive the completion of a the buffer task (with a FF link)?

    So i will have two task with a gap between them. The tasks may fluctuate in terms of start/completion dates, but a seperate task linked in between them will automatically fluctuate in duration along with them, to replace the gap between the two task. 

  4. 0
    Mike Testro ·

    Hi BenA buffer task is

    Hi Ben

    A buffer task is infinitely flexible between the movement of the start and finish links depending on both upstream and downstream movement.

    What more do you want?

    Best regards

    Mike T.

  5. 0
    Andrew Pearce ·

    The Hammock type activity

    The Hammock type activity will work if task 1 and 3 are both milestones. Add them to a hammock activity called Guard delivered building material