Cost display in Spreadsheet
In the Open Standard
Peter ScottMember for 21 years 6 months
- Created
- 0
- 4
0
I am displaying ’total cost’ and ’cost to date’ in the spreadsheet (ie tokens ’cost’ and ’actual cost’) QS has asked to see amount added in this valuation ie between progress periods. All the tokens I can find assume progress was on schedule last progress period. Can anyone help?